Worked example · Vibrating Screen

Near-size gravel feed

Most of the gravel passing fraction lies close to the opening, with only nine percent below half-size.

Live results

Screen deck and material split

Edit inputs
Screen deck and material split Four live readings and a schematic of the selected material-handling configuration. Full values follow the diagram. DECK AREA107.17ft²PASS EFF.74.72%UNDERSIZE88.47TPHOVERSIZE96.53TPH VIBRATING DECKMATERIAL SPLITOpening 0.5 inDry deckFeed185 TPHOversize96.53 TPHUndersize88.47 TPHTop deck Required / installed area167.45%Installed deck is below the estimated target area.

Installed deck is below the estimated target area.

All calculated values
Required live deck area
107.17ft²
Estimated passing efficiency
74.718%
Undersize product
88.466TPH
Oversize product
96.534TPH
True undersize in feed
118.4TPH
Undersize retained on deck
29.934TPH
Deck area at 90% recovery
107.17ft²
Aperture base capacity
1.503TPH/ft²
Corrected unit capacity
1.105TPH/ft²
Oversize correction
1.055
Half-size correction
0.69
Deck position correction
1
Wet screening correction
1
Density correction
1.01

Inputs

Unit system
Operating inputs
TPH
%
%
Percent of total feed smaller than half the selected aperture.
in
lb/ft³
ft²
%
Drive & model factors
TPH/ft²
0 uses the aperture curve. Enter the passing capacity per unit area at the stated reference conditions.

Worked solution

Starting case in US units

  1. Apply the 64% undersize fraction to the 185 TPH feed, giving 118.4 TPH of true undersize.
  2. The corrected unit capacity is 1.1 TPH/ft². The area required for 90% passing efficiency is 107.17 ft².
  3. With 64 ft² installed, predicted passing efficiency is 74.72%, splitting into 88.47 TPH passing and 96.53 TPH retained.

Try it. Increase the half-size fraction without changing total undersize. This increases estimated throughput per unit area.

More worked examples

Open a different starting case

Equations and assumptions

Aperture rating and corrections

C = C₀ · Fo · Fh · Fd · Fw · Fρ

The default C₀ is 2.2 × aperture(in)^0.55 short tons/h/ft². Reference conditions are 25% oversize, 40% half-size, 100 lb/ft³, top deck, dry screening and 90% recovery. Fo = 1 + 0.5(oversize fraction − 0.25), Fh = 1 + (half-size fraction − 0.40), and Fd = 1/0.9/0.8 by deck position (top/second/third respectively). Wet spray uses Fw = 1 + 0.3/(1 + aperture(in)²). Fρ scales with bulk density. The curve and corrections are illustrative VSMA-style estimates. Use an OEM rating and validate motion, media open area, bed depth and blinding before selection.

Live area and passing efficiency

A₉₀ = Qfeed · fᵤ / C   |   E = 1 − 0.1^(Ainstalled/A₉₀)
Arequired = A₉₀ · ln(1 − Etarget) / ln(0.1)

fᵤ is the fraction smaller than the aperture. This first-pass recovery curve is anchored at 90% for A₉₀. Its estimated recovery depends on the installed live area. Use a sampled and weighed feed and product mass balance to establish plant efficiency.

Stream split

Qpassing = Qfeed · fᵤ · E   |   Qretained = Qfeed − Qpassing

This model assumes coarse particles remain above the aperture. The oversize product includes unrecovered fines. Feed, passing and retained rates use the same mass basis.

References