Worked example
Asphalt truckloads for a 24,000 ft² lot
A parking lot bid includes 24,000 ft² of asphalt at a combined 4 in compacted thickness. Trucks carry up to 22 short tons of asphalt each.
Estimate
Asphalt to order
- Material cost uses ordered asphalt only. Confirm mix density, lift limits and load capacity with the supplier.
- Asphalt order · equivalent
- 552.476 t
- Asphalt before waste
- 580 short ton
- Compacted aggregate base
- 1,120 short ton
- Compacted asphalt volume
- 296.296 yd³
- Asphalt haul loads
- 28
- Asphalt material cost
- 59,073 $
Download
Working this example
Starting estimate 609 short tonAsphalt to order
If base and surface mixes differ, calculate each lift with its own density, price and haul schedule.
Questions & answers
Does a 4 in total thickness mean one paving lift on this lot?
The takeoff uses a combined thickness for quantity. The mix, paving specification and compaction plan govern the allowable lift sequence.
How do I reflect restricted haul payload at the parking lot entrance?
Enter a lower usable payload. The tonnage stays fixed and the haul count increases when the order needs more trips.