Worked example

Asphalt overlay on an existing milled base

A milled private lane gets an initial 1.5 in compacted overlay estimate on sound existing base. The thickness flag prompts a mix check.

Inputs

Measurement system
ft²
in
Enter final rolled thickness. Typical inputs are 2–6 in.
lb/ft³
in
%
$/short ton
short ton
PAVEMENT SECTIONCompacted asphalt lift and aggregate base. The asphalt mass is shown under the section. PAVEMENT SECTION Asphalt 1.5 inSUBGRADE79.72 short ton orderedArea 8,400 ft²

Estimate

Asphalt to order
79.716 short ton
  • Material cost uses ordered asphalt only. Confirm mix density, lift limits and load capacity with the supplier.
  • The compacted lift falls outside the 2–6 in planning range. Check the mix and paving specification.
Asphalt order · equivalent
72.317 t
Asphalt before waste
76.65 short ton
Compacted aggregate base
0 short ton
Compacted asphalt volume
38.889 yd³
Asphalt haul loads
5
Asphalt material cost
10,203.65 $
Download

Working this example

Starting estimate 79.716 short tonAsphalt to order

Separate localized leveling and patch quantities before budgeting new mix for the full area.

See the calculator formulas and assumptions

Questions & answers

Why is aggregate base zero in this overlay estimate?

The scope carries the existing base forward. Add new aggregate volume only where replacement is specified.

How do low spots influence a thin overlay quantity?

Low spots require extra leveling mix. Measure their area and average fill depth separately from the nominal overlay.