Worked example
Asphalt and stone for a 5,400 ft² apron
A delivery apron uses 3.5 in of asphalt and 10 in of compacted aggregate over 5,400 ft². Both material quantities are shown for bid comparison.
Estimate
Asphalt to order
- Material cost uses ordered asphalt only. Confirm mix density, lift limits and load capacity with the supplier.
- Asphalt order · equivalent
- 113.419 t
- Asphalt before waste
- 115.76 short ton
- Compacted aggregate base
- 310.5 short ton
- Compacted asphalt volume
- 58.333 yd³
- Asphalt haul loads
- 7
- Asphalt material cost
- 14,752.77 $
Download
Working this example
Starting estimate 125.024 short tonAsphalt to order
Measure the stone footprint from the section if it extends past the asphalt. Calculate that extra strip on its own.
Questions & answers
Does the asphalt waste percentage increase the apron stone tonnage?
The waste allowance in this worksheet applies to asphalt. Budget separate stone allowances for the base supply.
How should I handle an aggregate base that extends past the apron?
Measure the expanded base area in a separate estimate. This worksheet applies both sections to the entered footprint.