ConcreteEarthLab

Worked example

Alley paving with 8-ton haul payloads

An alley can accept only small trucks, so the takeoff uses an 8 short ton usable payload and a 2.5 in compacted asphalt lift.

Inputs

Measurement system
ft²
in
Enter final rolled thickness. Typical inputs are 2–6 in.
lb/ft³
in
lb/ft³
%
$/short ton
short ton
PAVEMENT SECTIONCompacted asphalt lift and aggregate base. The asphalt mass is shown under the section. PAVEMENT SECTION Aggregate 4 inAsphalt 2.5 inSUBGRADE57.8 short ton orderedArea 3,560 ft²

Estimate

Asphalt to order
57.802 short ton
  • Material cost uses ordered asphalt only. Confirm mix density, lift limits and load capacity with the supplier.
Asphalt order · equivalent
52.437 t
Asphalt before waste
53.03 short ton
Compacted aggregate base
77.13 short ton
Compacted asphalt volume
27.469 yd³
Asphalt haul loads
8
Asphalt material cost
6,936.22 $
Download

Working this example

Starting estimate 57.802 short tonAsphalt to order

Align the delivery intervals with paving speed and plant distance to avoid an interrupted placement sequence.

See the calculator formulas and assumptions

Questions & answers

How do small haul trucks affect the asphalt tonnage for this alley?

Truck size changes the number of trips, while the asphalt tonnage depends on paved area, thickness, density and waste.

Why is the final scheduled alley load likely partial?

The truck count is rounded up. Subtract the payload of all earlier full loads from the asphalt order to estimate the last load.