Worked example
Alley paving with 8-ton haul payloads
An alley can accept only small trucks, so the takeoff uses an 8 short ton usable payload and a 2.5 in compacted asphalt lift.
Estimate
Asphalt to order
- Material cost uses ordered asphalt only. Confirm mix density, lift limits and load capacity with the supplier.
- Asphalt order · equivalent
- 52.437 t
- Asphalt before waste
- 53.03 short ton
- Compacted aggregate base
- 77.13 short ton
- Compacted asphalt volume
- 27.469 yd³
- Asphalt haul loads
- 8
- Asphalt material cost
- 6,936.22 $
Download
Working this example
Starting estimate 57.802 short tonAsphalt to order
Align the delivery intervals with paving speed and plant distance to avoid an interrupted placement sequence.
Questions & answers
How do small haul trucks affect the asphalt tonnage for this alley?
Truck size changes the number of trips, while the asphalt tonnage depends on paved area, thickness, density and waste.
Why is the final scheduled alley load likely partial?
The truck count is rounded up. Subtract the payload of all earlier full loads from the asphalt order to estimate the last load.