Metric asphalt for a 960 m² access road

This metric access road covers 960 m² with a 75 mm asphalt section and a 175 mm aggregate base. Cost is entered in dollars per metric tonne.

Inputs

Measurement system
m²
mm
Enter final rolled thickness. Typical inputs are 2–6 in.
kg/m³
mm
kg/m³
%
$/t
t
PAVEMENT SECTIONCompacted asphalt lift and aggregate base. The asphalt mass is shown under the section. PAVEMENT SECTION Aggregate 175 mmAsphalt 75 mmSUBGRADE180.4 t orderedArea 960 m²

Estimate

Asphalt to order
180.403 t
  • Material cost uses ordered asphalt only. Confirm mix density, lift limits and load capacity with the supplier.
Asphalt order · equivalent
198.86 short ton
Asphalt before waste
167.04 t
Compacted aggregate base
362.88 t
Compacted asphalt volume
72 m³
Asphalt haul loads
11
Asphalt material cost
22,550.4 $
Download

Working this example

Starting estimate 180.403 tAsphalt to order

Confirm the plant ticket unit. A metric tonne weighs 1,000 kg and a US short ton weighs 2,000 lb.

See the calculator formulas and assumptions

Questions & answers

What is the asphalt volume for the 75 mm metric access road?

960 m² × 0.075 m gives 72 m³ of compacted asphalt before waste.

Why does the price per tonne change when switching this access road to US units?

The unit price changes to dollars per short ton so the total material cost remains the same.