Offshore carbon steel coupon
A cleaned carbon steel coupon from a pipe spool lost 428 mg over 720 hours. The total exposed surface was 38.5 cm².
Inputs
SI unitsUse cleaned mass loss, total exposed area and the actual exposure duration. Equivalent weights in the presets are illustrative.
- Penetration
- 0.17 mm/yr
- Areal loss
- 3.71 g/(m²·day)
- Current equiv.
- 14.81 µA/cm²
- US rate
- 6.78 mpy
Coupon exposure cell
SchematicCompare with the project limit and inspect for pits. Localized attack can exceed the coupon average.
Calculation details
- Metric penetration
- 0.1721 mm/yr
- US penetration
- 6.7771 mpy
- Areal mass-loss rate
- 3.71 g/(m²·day)
- Equivalent corrosion current
- 14.81 µA/cm²
- mm/yr per µA/cm²
- 0.011616
Inputs used
- Calculation mode
- Coupon mass loss
- Alloy preset
- Carbon steel
- Cleaned mass loss
- 428 mg
- Exposed area
- 38.5 cm²
- Exposure duration
- 720 hr
- Alloy density
- 7.86 g/cm³
- Equivalent weight
- 27.92 g/equiv
Worked calculation
Starting values · SI- 0.428 g ÷ (38.5 cm² × 720 hr) gives 0.00002 g/(cm²·hr).
- Multiply the mass flux by 87,600 ÷ 7.86 to get 0.17208 mm/yr. The G1 mpy constant gives 6.77715 mpy.
- The equivalent current density is 14.81465 µA/cm².
Review the average penetration beside the areal loss. If microscopy finds pits, keep the maximum pit depth as a separate observation.
Method and limits
Normalize the exposure
Use mass loss W in grams, total exposed area A in cm², duration T in hours and density ρ in g/cm³. Include both faces and edges if these were exposed.
Calculate penetration and areal loss
Average penetration = K × W ÷ (A × T × ρ). K is 87,600 for mm/yr and 3,450,000 for mpy. Areal mass loss = 240,000 × W ÷ (A × T) in g/(m²·day). The two published K values are independently rounded.
Convert using equivalent weight
The Faraday relation is mm/yr = 0.00327 × i × EW/ρ, where i is in µA/cm². Divide by the coefficient to convert back. In either Faraday mode, mpy = mm/yr ÷ 0.0254.