Compare six electronics workstations and a 45-second test interval with a 36-second takt requirement.

Takt = Net available time ÷ Demand

Baseline reading

A 45-second station limits the theoretical shift to 720 boards. Station 5 also exceeds 36 seconds and would constrain a test-station improvement.

What to test

Model a realistic parallel fixture and check both test and pack-out again. Verify fixture changeover and operator availability before scheduling the extra output.

Currency labels entered amounts. Exports record the selected display units.

Inputs

Shift and demand
sec
sec
Observed workstation cycles
sec
sec
sec
sec
sec
sec

Results

Takt time
36 sec
Bottleneck station
Station 3
Bottleneck cycle
45 sec

Bottleneck alert. Station 3 exceeds customer takt.

Yamazumi station balance
Yamazumi station balance Station cycle bars with the dashed takt threshold. Ochre identifies stations above takt. CUSTOMER TAKT 36 sec012.625.237.850.4Station 131Station 234Station 345Station 430Station 537Station 628sec
Maximum steady-state shift output
720
Output minus demand
-180
Net available shift time
32,400 sec
Total work content
205 sec
Theoretical station equivalents
5.69444
Minimum whole stations
6
Line balance efficiency
75.9259%
Balance delay
24.0741%

Model notes

Use station times for one unit, with the same product and work method. Maximum output assumes a staffed, paced line in steady state and excludes start-up fill and starvation.

The minimum whole-station count is a workload bound. Precedence, indivisible tasks, tooling and travel can require more operators or stations.

View the equations

Frequently asked questions

How do I model two fixtures running staggered board tests?

Enter the observed interval between board departures from the combined station. Include shared loading, connection, and disposition work in that interval.

Does a retest loop belong in the electronics cycle baseline?

Decide whether the baseline reflects standard first-pass work or demonstrated effective output. Keep the retest load visible as its own estimate when studying the bottleneck.