Worked example · Line balance
Feeder cell staffing from work content
Use 193 seconds of observed work content to bound staffing for a three-station feeder assembly cell.
Takt = Net available time ÷ Demand
Baseline reading
Work content is 2.14 station equivalents at the 90-second pace. Three whole stations are needed even before precedence and walk time are considered.
What to test
List subtasks within each station cycle. Use the underlying task durations to evaluate staffing changes and a practical station layout.
Worksheet inputs
Inputs
Results
- Takt time
- 90 sec
- Bottleneck station
- Station 1
- Bottleneck cycle
- 73 sec
- Maximum steady-state shift output
- 271
- Output minus demand
- 51
- Net available shift time
- 19,800 sec
- Total work content
- 193 sec
- Theoretical station equivalents
- 2.14444
- Minimum whole stations
- 3
- Line balance efficiency
- 88.1279%
- Balance delay
- 11.8721%
Model notes
Use station times for one unit, with the same product and work method. Maximum output assumes a staffed, paced line in steady state and excludes start-up fill and starvation.
The minimum whole-station count is a workload bound. Precedence, indivisible tasks, tooling and travel can require more operators or stations.
Frequently asked questions
Could two feeder operators meet takt by working faster?
At the entered standard, 193 seconds of work exceeds the combined 180 seconds available per takt for two operators. Document a verified work-content reduction first.
How should a shared feeder replenisher be counted in staffing?
Add per-unit work done by the line operators to station cycles. Track dedicated replenisher staffing separately as an external resource to the cell.