Worked example · Line balance
Electronics test station capacity
Compare six electronics workstations and a 45-second test interval with a 36-second takt requirement.
Takt = Net available time ÷ Demand
Baseline reading
A 45-second station limits the theoretical shift to 720 boards. Station 5 also exceeds 36 seconds and would constrain a test-station improvement.
What to test
Model a realistic parallel fixture and check both test and pack-out again. Verify fixture changeover and operator availability before scheduling the extra output.
Worksheet inputs
Inputs
Results
- Takt time
- 36 sec
- Bottleneck station
- Station 3
- Bottleneck cycle
- 45 sec
- Maximum steady-state shift output
- 720
- Output minus demand
- -180
- Net available shift time
- 32,400 sec
- Total work content
- 205 sec
- Theoretical station equivalents
- 5.69444
- Minimum whole stations
- 6
- Line balance efficiency
- 75.9259%
- Balance delay
- 24.0741%
Model notes
Use station times for one unit, with the same product and work method. Maximum output assumes a staffed, paced line in steady state and excludes start-up fill and starvation.
The minimum whole-station count is a workload bound. Precedence, indivisible tasks, tooling and travel can require more operators or stations.
Frequently asked questions
How do I model two fixtures running staggered board tests?
Enter the observed interval between board departures from the combined station. Include shared loading, connection, and disposition work in that interval.
Does a retest loop belong in the electronics cycle baseline?
Decide whether the baseline reflects standard first-pass work or demonstrated effective output. Keep the retest load visible as its own estimate when studying the bottleneck.