Worked example · IEC 60364 · NEC 250 context

Adjustable instantaneous pickup

TN-S and TN-C-S loop impedance, protection threshold and adiabatic CPC area.

An adjustable breaker is modeled with a required 7.5 × pickup and a lower available voltage factor.

Device threshold met

Compared with the pickup for the selected protective device.

Fault loop impedance
0.395 Ω
Earth-fault current
535.7 A
Maximum permissible Zₛ
0.44783 Ω
CPC area at modeled current
1.4985 mm²

Inputs

Circuit return path
V
×
Ω
Ω
Ω
×
Protection and CPC
A
×
s
A√s/mm²
Use the value for the material, insulation and starting temperature.

Phase-to-PE fault loop

Live schematic
Loop Zs0.395 ΩFault current535.7 AZs limit0.4478 ΩCPC area1.498 mm²TN-S · METALLIC LOOPR₁ phase 0.1464 ΩR₂ protective 0.1586 ΩEarthed sourceFaulted loadZₑ 0.09 ΩPROTECTIVE DEVICE CHECKProspective earth-fault current535.7 ADevice threshold472.5 ALoop impedance headroom0.05283 ΩLoop impedance / limit88.2%
The fault returns on PE and, in TN-C-S, through the upstream PEN. The parallel earth paths are omitted.

Derived values & comparisons
Protective device threshold472.5 A
Zₛ headroom0.052831 Ω
Fault current above threshold63.196 A
Warm phase / CPC resistance0.1464 Ω / 0.1586 Ω
Next size for modeled fault duty1.5 mm²
Supply voltage after cₘᵢₙ211.6 V

Screening scope. Verify actual loop impedance, the manufacturer’s clearing curve and device breaking capacity. Size the CPC for worst-case let-through I²t and the applicable minimum area. NEC 250 uses separate bonding and equipment grounding provisions.

Try this. Review the maximum loop impedance, then compare the adiabatic area at two clearing times.

Calculation method

IEC 60364-4-41 and IEC 60364-5-54. Zₛ = Zₑ + (R₁ + R₂) × temperature factor, with the floor current Iₑꜰ = U₀cₘᵢₙ/Zₛ and limit Zₛ,ₘₐₓ = U₀cₘᵢₙ/Iₐ. Resistances are added as a scalar screening approximation.

The B, C and D defaults use 5, 10 and 20 times In, respectively. For a gG fuse, enter the total-clearing current read from the manufacturer’s curve at the entered time. Use the manufacturer’s curve to determine disconnection time.

The adiabatic calculation is S = Iₑꜰ√t/k for the entered duty. Check the maximum relevant I²t and the applicable mechanical minimum separately. NEC Article 250 describes the effective ground-fault current path and has its own conductor sizing requirements.

Standards and model assumptions