Tight baffle spacing and pressure penalty

A compact design reduces baffle spacing to increase shell-side velocity.

Segmental baffle cutaway

Aₛ = DₛB(p − Dₒ)/p · Nu = 0.36 Re⁰·⁵⁵ Pr¹ᐟ³ (μ/μwall)⁰·¹⁴

Edit inputs ↓
Crossflow area
0.01292m²
Shell velocity
2.1672m/s
Shell hₒ
9,944.1W/(m²·K)
Shell ΔP
1,295.9kPa
Segmental baffle cutawaySHELL INLET →SEGMENTAL CUT49 baffles22 % of shell IDB/Dₛ 0Spacing windowB/Dₛ 1.35
The baffle cut sets the drawn window. The spacing marker shows the entered B/Dₛ compared with the screening band.
  • Baffle spacing falls outside the preliminary spacing window.
  • Kern coefficients use the nominal 25% cut. The window geometry reflects the entered cut.

Inputs

m
m
%
m
L/min
kg/m³
mPa·s
mPa·s
W/(m·K)
kJ/(kg·K)

Calculated results

Bundle crossflow area
0.01292 m²
Crossflow velocity
2.1672 m/s
Shell-side film hₒ
9,944.1 W/(m²·K)
Shell-side pressure drop
1,295.9 kPa
Equivalent diameter
13.771 mm
Shell Reynolds number
48,437
Gross baffle window
0.05924 m²
Estimated segmental baffles
49
Crossflow sections
50
Shell mass flux
2,145.5 kg/(m²·s)
Prandtl number
4.1126
Kern friction factor
0.22907
Baffle spacing / shell ID
0.13971
Screening minimum spacing
0.136 m

Worked solution

Preset calculation · Metric SI

  1. From the shell bore, spacing, and clear pitch, find 0.01292 m² available for crossflow.
  2. Use the pitch cell to obtain a hydraulic equivalent diameter of 13.771 mm and Reynolds number of 48,437.
  3. Apply the Kern screen across 50 sections to estimate 9,944.1 W/(m²·K) for hₒ and 1,295.9 kPa for pressure loss.

The spacing marker falls below the screening band. Increase spacing and compare the drop in hₒ with the drop in pressure loss.

Calculation basis

Kern crossflow area uses the notional tube row at the shell equator. Equivalent diameter comes from the open area and wetted perimeter of a square or triangular pitch cell.

The 25% nominal baffle-cut correlation estimates shell-side hₒ and pressure drop. The entered cut changes the gross segment window and diagram. Leakage, bypass, window obstructions, and nozzle losses require a more detailed method.

The spacing screen runs from the larger of 0.2Dₛ and 50 mm to Dₛ. Maximum unsupported length and vibration depend on the actual tube material and layout.