Flat titanium plate resistance

A thin corrosion-resistant plate separates two clean liquid streams with relatively high film coefficients.

Thermal resistance stack

U = 1 / ΣR · Rwall,tube = rₒ ln(rₒ / rᵢ) / k

Edit inputs ↓
Clean U
1,932W/(m²·K)
Service U
1,486.8W/(m²·K)
Cleanliness
76.955%
Largest term
Outside film
Thermal resistance stackRESISTANCE TERMSHARE OF TOTALInside film33.039 %Inside fouling9.6639 %Metal wall3.7339 %Outside fouling13.381 %Outside film40.183 %0% clean80% screen100% clean
Each segment adds resistance on the same surface-area basis. The longest segment makes the largest contribution.
  • Service U is below 80% of clean U. Review the fouling allowance and cleaning basis.

Inputs

W/(m²·K)
W/(m²·K)
m²·K/W
m²·K/W
mm
W/(m·K)

Calculated results

Clean overall U
1,932 W/(m²·K)
Fouled service U
1,486.8 W/(m²·K)
Cleanliness
76.955 %
Controlling resistance
Outside film
Total fouled resistance
0.00067261 m²·K/W
Inside film resistance
0.00022222 m²·K/W
Inside fouling resistance
6.50e-5 m²·K/W
Wall resistance
2.51e-5 m²·K/W
Outside fouling resistance
9.00e-5 m²·K/W
Outside film resistance
0.00027027 m²·K/W
Fouling loss in U
23.045 %

Worked solution

Preset calculation · Metric SI

  1. Put both films, both fouling terms, and the wall on one surface basis. The wall contributes 2.51e-5 m²·K/W.
  2. Sum the resistances to get 0.00067261 m²·K/W. Its reciprocal gives service U of 1,486.8 W/(m²·K).
  3. Omit the fouling terms to get clean U of 1,932 W/(m²·K), then divide service U by clean U for 76.955 % cleanliness.

Wall resistance is t/k on the same area basis as both films. Vary plate thickness to see how little it contributes here.

Calculation basis

For a tube, results refer to outside surface area. Multiply inside film and inside fouling by rₒ/rᵢ. The cylindrical wall uses rₒ ln(rₒ/rᵢ)/k.

For a flat plate, both sides have the same area and wall resistance is thickness divided by conductivity. Clean U omits both fouling allowances.

Enter service-specific fouling factors on their local surface basis, using the project or TEMA allowance. The 80% cleanliness check is a worksheet screening value.

Methodology and references