Worked example

Concrete around actual 5½ in square fence posts

Six posts support a 30 ft straight run at 6 ft spacing. Estimate 50 lb bags for a 12 in round hole with a 36 in concrete depth and a 5½ in square post.

Project inputs

Run and bays
ft
ft
Pickets
in
in
Footings
in
in
in

Material & layout estimate

Posts to set

6
Gate posts included
0
Fence bays
5
Even post center spacing
6 ft
Fence rails
15
Fence pickets
60
Pickets per bay
12
Concrete per post
1.73 ft³
Whole bags per post
5
Bags for separate pours
30
Bags for a combined pour
28

This layout assumes a straight, level run and evenly divided sections between gates. Allow for gate hardware, gate infill, corners, and stock cuts separately.

Confirm footing geometry, frost depth, wind exposure, and bag yield for the chosen fence and site.

Fence elevation & post footing Schematic
Fence elevation & post footingPosts to set: 6. Gate posts included: 0. Fence bays: 5. Even post center spacing: 6 ft FENCE ELEVATION6 ft high · 30 ft run5 bays · 6 posts0 gate openingsPOST FOOTING12 in diameter36 in deep · 5 bags/post

Starting estimate

Separate pours round to five bags for each hole, or 30 total. A combined pour requires 28 when fractional yields can be shared.

Posts to set
6
Whole bags per post
5
Bags for separate pours
30
Bags for a combined pour
28

How the estimate works

  1. Subtract gate center-to-center widths from the run and distribute the remaining length evenly between fence sections. Divide each section into bays within the spacing limit.
  2. Subtract the post width from each bay’s center span to find the clear picket width. Divide by picket pitch, accounting for the first and last board.
  3. Estimate concrete as round hole volume minus submerged square post volume. Round up by the selected bag yield per hole or for a combined pour.

Questions and answers

Why subtract the actual 5½ in square area from each hole?

The buried post occupies space in the hole. The concrete estimate fills the remaining cross-section across the entered concrete depth.

Does this 36 in post hole depth include a gravel drain bed?

Enter concrete depth only. If the bottom includes a separate gravel layer, subtract its depth from the per-hole concrete measurement.