Stairwell with a 90-minute survey

Enter measurements at both time points, using readings from the same walking path. The survey catches a larger uniformity ratio at the end.

Path and initial readings
ft
ft
fc
fc
fc
fc
fc
fc
Emergency circuit and inverter
lm/W
W
VA
×
Initial avg.
1.25fc
90-min avg.
0.71fc
Worst max:min
42.5:1
Battery bank
8.88Ah

Initial and 90-minute path light levels

Edit inputs ↓
Initial and 90-minute path light levelsEGRESS FLOOR LEVELSURVEY RANGESInitial surveyavg 1.25 fc90-minute surveyavg 0.71 fcPath 38 ft40:1 limitWorst uniformity42.5:1
Markers show the minimum, mean and maximum for the entered survey. The ranges do not assign values to specific points on the path.

NFPA 101 egress screen

Review needed
OutsideThresholdWithin
  • Initial mean1.25 / ≥ 1 fc within screen
  • Initial minimum0.15 / ≥ 0.1 fc within screen
  • 90-minute mean0.71 / ≥ 0.6 fc within screen
  • 90-minute minimum0.08 / ≥ 0.06 fc within screen
  • Initial max / min18.667 / ≤ 40 :1 within screen
  • 90-minute max / min42.5 / ≤ 40 :1 outside screen

The 90-minute light floors are 60% of the initial code floors. The 40:1 limit applies to both readings.

Additional readings
Walking surface area190ft²
Total initial fixture output4,750lm
Emitted flux per floor area25lm/ft²
Initial minimum0.15fc
Initial maximum2.8fc
Initial max / min18.67:1
90-minute minimum0.08fc
90-minute maximum3.4fc
90-minute max / min42.5:1
Inverter real load50W
Inverter apparent load65VA
Assumed fixture power factor0.769
Estimated DC current4.73A
DC energy before derating85.23Wh

Worked calculation

US customary results for the original preset.

  1. The initial average and minimum are 1.25 fc and 0.15 fc. The corresponding 90-minute values are 0.71 fc and 0.08 fc.
  2. The worst maximum-to-minimum ratio is 42.5:1 against the 40:1 limit.
  3. The inverter supplies 65 VA and 50 W. For 90 minutes, the estimated derated bank is 8.88 Ah.

Calculation method

Use floor-level readings along the egress route. Enter measured 90-minute values where available, or apply the same end-of-discharge factor to each initial reading.

NFPA 101 screening floors
Initial avg ≥ 1 fc, min ≥ 0.1 fc · At 90 min avg ≥ 0.6 fc, min ≥ 0.06 fc
Uniformity at both times
Emax/Emin ≤ 40:1 · a zero minimum fails the screen
Inverter and battery
VAload = count × VA per fixture · Ah = Wload × 1.5 h × derating/(VDC × η)

Confirm the locally adopted edition, listed emergency equipment, inrush and battery discharge curves. Field-test the full required emergency duration.