Good output 542.8 parts/h
Cycle time 26 s
Unit cost 0.527 USD/part
Machine hours 184.24 h
Molding cycle and cost allocation Live schematic
4 CAV · 139 g 542.8 parts/h CYCLE TIME 26 s Fill 1.5 s Hold 6 s Cool 14 s Eject 4.5 s UNIT COST USD 0.527 Resin Machine Tooling
Quote covers unit cost
0% 100% of quote 125%+
Uses good parts after scrap. The break-even count divides tooling cost by selling price less variable cost.
Share link Reset defaults JSON CSV SVG PNG (2×) Print A4
Calculation details
Shot mass 139 g Gross resin per good part 0.094 USD/part Regrind credit per good part 0.0036 USD/part Net resin per good part 0.0904 USD/part Machine per good part 0.1566 USD/part Tooling per good part 0.28 USD/part Order production cost 52,699.61 USD Quote margin per part 0.323 USD/part Tooling payback quantity 46,435
Model and assumptions
Good parts/h = 3600 × N × (1−scrap)/t_cycle. Tooling per part = CapEx/quantity. Payback parts = ceil[CapEx/(price − variable cost)].
Enter distinct cycle stages, counting only additional cooling after hold. Scrap is the average fraction of part impressions rejected. Regrind credit applies to recovered runner and rejected-part resin at the entered value fraction. Production hours are averages at steady operation. Add setup labor, downtime, packing, freight and any other quoted charges to your separate commercial estimate. Currency is USD in both measurement systems.
Methodology and sources
C_unit = C_resin + C_press + CapEx ÷ order quantity
Inputs Cavities 4 Fill time 1.5 s Pack and hold time 6 s Additional cooling after hold 14 s Mold open, eject and close 4.5 s Part scrap rate 2 % Net part mass 32 g Runner and sprue mass per shot 11 g Virgin resin price 2.65 USD/kg Runner and rejects recovered 60 % Regrind value vs virgin price 65 % Press hourly rate 85 USD/h Tooling CapEx 28,000 USD Order quantity of good parts 100,000 Quoted selling price 0.85 USD/part
Results Good output 542.8 parts/h Cycle time 26 s Unit cost 0.527 USD/part Machine hours 184.24 h Shot mass 139 g Gross resin per good part 0.094 USD/part Regrind credit per good part 0.0036 USD/part Net resin per good part 0.0904 USD/part Machine per good part 0.1566 USD/part Tooling per good part 0.28 USD/part Order production cost 52,699.61 USD Quote margin per part 0.323 USD/part Tooling payback quantity 46,435
Quote covers unit cost. Uses good parts after scrap. The break-even count divides tooling cost by selling price less variable cost.
4 CAV · 139 g 542.8 parts/h CYCLE TIME 26 s Fill 1.5 s Hold 6 s Cool 14 s Eject 4.5 s UNIT COST USD 0.527 Resin Machine Tooling
Enter distinct cycle stages, counting only additional cooling after hold. Scrap is the average fraction of part impressions rejected. Regrind credit applies to recovered runner and rejected-part resin at the entered value fraction. Production hours are averages at steady operation. Add setup labor, downtime, packing, freight and any other quoted charges to your separate commercial estimate. Currency is USD in both measurement systems.