Closure strips for a 40 ft gable roof
A ribbed metal gable has 40 ft eaves and continuous closures at both eaves and on both sides of the ridge.
Worked calculation
There are four 40 ft runs. Ten 4 ft pieces cover each run, giving 40 closure strips before any breakage allowance.
Change the inputs to test your own measurements. Reset restores this example.
Results
LiveCorrect the highlighted inputs to update your results.
- Total panels
- Panel cut length
- Panels per side
- Eave length with overhangs
- Last panel net strip
- Roof panel coverage
- Ridge or high-side trim
- Ridge or high-side pieces
- Rake trim
- Rake pieces
- Eave drip trim
- Eave drip pieces
- Closure strip length
- Closure strips
- Clip or screw positions
Worksheet inputs US customary
- Roof shape
- Gable · two equal sides
- Panel length input
- Building span and pitch
- Building length parallel to eave
- 40 ft
- Full horizontal building span
- 26 ft
- Roof pitch
- 4:12
- Rake overhang at each end
- 0 ft
- Extra cut length along slope
- 2 in
- Panel system
- Ribbed (screw estimate)
- Panel net coverage width
- 24 in
- Trim stock length
- 10 ft
- Overlap at each trim joint
- 0.5 ft
- Closure strip coverage per piece
- 4 ft
- Fastening points per 100 ft² (9.29 m²)
- 80
Apply this example to your roof
Match panel minimum slope, field detailing, clips, edge fastening and thermal movement to the system drawings. Confirm manufacturable cut lengths, delivery limits and exact trim and closure profiles before ordering.
Frequently asked questions
Why are there four closure runs on this two-sided gable?
The planning model counts a lower and upper closure on each side. Verify whether the specified ridge uses a vented closure.
Do I buy identical closure strips for all four runs?
Match the panel profile and the upper and lower details. The total length helps price the scope, while the installation details determine the parts.