WaterTreatLab

Ion exchange / Worked example

Resin Capacity Exhausted before One Day

Find the service interval, remaining capacity and flow warning for a heavily loaded 20 ft³ resin bed.

Inputs

Water & resin
gal/d
gpm
gpg
ft³
%
Run length & metals
d
d
mg/L
gpg per mg/L
mg/L
gpg per mg/L

Results

US customary
Run length
0.6 d
Treated per cycle
14,400 gal
Salt per cycle
120 lb
Peak service loading
5.5 gpm/ft³ 44.115 BV/h
Sodium-cycle resin vesselLive diagram
Sodium-cycle resin vesselCapacity remaining after the entered time in service. Hard feedAdjusted hardness25 gpgPeak resin loading5.5 gpm/ft³Softened outletUsable capacity remaining0 %ExhaustedRegenerated
Capacity remaining after the entered time in service.
Review the operating point
  • Peak loading exceeds 5 gpm/ft³. Check resin leakage and vessel hydraulics.
  • Elapsed service reaches or exceeds the estimated usable capacity.
Adjusted hardness
25 gpg
Daily hardness load
600,000 grains/d
Usable capacity
360,000 grains
Rated capacity per resin volume
20,000 grains/ft³
Salt per 30 days
6,000 lb/30 d
Resin for target interval
66.667 ft³
Usable capacity remaining
0 %

For engineering planning. Operators must follow site-specific permits, chemical safety data sheets (SDS), manufacturer specifications, and certified regulatory sampling requirements.

Worked solution

These steps walk through the starting inputs in US customary units. Edit the calculator above to test a different operating point.

  1. Load is 24,000 × 25 = 600,000 grains/day. The 360,000 usable grains last 0.60 day.
  2. After one day the model shows no usable capacity remaining. Peak service is 110 ÷ 20 = 5.5 gpm/ft³.

More worked examples

Equations & conventions

Compensated hardness
H = Hᵣₐw + kꜰₑ[Fe] + kₘₙ[Mn]

US hardness uses gpg, where 1 gpg is approximately 17.118 mg/L as CaCO₃. The editable default Fe/Mn allowances are planning inputs. Use the resin supplier’s corrections.

Usable capacity
C = Vᵣₑₛᵢₙ × Cᵣₐₜₑ𝒹 × (1 − reserve)

The planning curve uses 20,000, 27,000 and 30,000 grains/ft³ at 6, 10 and 15 lb salt/ft³. Capacity and leakage vary by resin and regeneration conditions.

Run length and resin volume
Vcycle = C / H, t = Vcycle / Qday

Daily hardness load is Qday × H. For resin at a target interval, multiply that load by the days and divide by usable capacity per unit resin.

Salt and service loading
Salt/regeneration = Vᵣₑₛᵢₙ × salt rate

Divide salt per regeneration by the run length and multiply by 30 for average 30-day consumption. Peak service flow divided by resin volume gives gpm/ft³ or bed volumes per hour.

Planning basis

The 1–5 gpm/ft³ service range is a C100 bulletin reference. Capacity can change with water chemistry, bed depth, flow and resin condition. Combined Fe/Mn above 0.5 mg/L calls for pretreatment and resin review under conventional waterworks guidance.

Questions

Can a larger vessel fix both warnings in this example?

More resin can improve hardness run length and reduce volume-normalized service flow. Check resin leakage, vessel cross-section and distributor hydraulics together.