WeldMetalLab

API 1104 · ASME B31.3

NPS 12 compound bevel on heavy wall

A 70° primary bevel transitions to an 18° outer included angle on the Schedule 80 joint.

Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.

Inputs

Pipe & preparation
°
°
in
Measure outwards from the top of the root land.
in
in
%
Passes & cycle
lb/in³
in²
in
in/min
in/min
in/min
min
min

Live weld sheet

Updated from inputs
Girth-weld groove sectionDeposited filler per joint 3.084 lb. Estimated passes 9. Joint arc time 50.52 min. Total joint cycle 62.52 min NET FILLER3.084lbPASS COUNT9ARC TIME50.52minJOINT CYCLE62.52min GIRTH-WELD GROOVE SECTION Wall 0.688 inR1 · H1 · F5 · C2NPS 12 CYCLE TIME BUDGETPASS
Pass · within screen

Cycle time budget · 62.52 min planned vs 70 min budget.

Result details

Deposited filler per joint3.084 lb
Estimated passes9
Joint arc time50.52 min
Total joint cycle62.52 min
Effective wall0.688 in
Pipe outside diameter12.75 in
Pipe bore11.374 in
Groove centroid circumference38.31 in
Outside circumference40.06 in
Root circumference35.73 in
Groove mouth width0.54 in
Uncapped groove section0.262 in²
Groove and cap volume10.87 in³
Filler purchase per joint3.352 lb
Root passes1
Hot passes1
Fill passes5
Cap beads2
Cycle time margin7.48 min

Worked example

Starting inputs

Nominal pipe size
NPS 12
Wall source
Schedule 80
Bevel profile
Compound V
Primary included angle
70 °
Outer included angle
18 °
Depth to bevel break
0.2 in
Root opening
0.125 in

Baseline results

Deposited filler per joint
3.084 lb
Estimated passes
9
Joint arc time
50.52 min
Total joint cycle
62.52 min

The 0.262 in² groove runs around a 38.31 in centroid circumference before cap allowance. The sequence adds 1 root, 1 hot, 5 fill and 2 cap passes over 50.52 min of arc time.

Try it. Switch to a single V while holding wall and primary angle fixed. The outer groove opens farther and the weld volume increases.

Calculation method

V = ∫ 2πr·w(r)dr + A꜀·π·OD · Arc time = Σ pass length / travel speed

The model integrates the piecewise linear groove width at each radius. Cap reinforcement is a percentage of groove area revolved at the outside diameter. Schedule presets cover a subset of common B36.10 walls. Confirm actual wall and ovality at the joint.

Reserve one root pass and an optional hot pass. Cap beads must cover the groove mouth and deposit the entered extra cap area. Root, hot and cap allowances are 0.60, 0.75 and 0.80 times the entered fill area per pass. Apply the unused cap-bead area to the groove, then round up the remaining fill passes. Root, hot/fill and cap times use the root, centroid and outside circumferences.

Cycle time adds the entered fit-up, interpass and handling allowance. Actual pass placement, reinforcement profile, deposition rates and essential variables come from the qualified procedure.

References

More worked examples