WeldMetalLab

API 1104 · ASME B31.3

NPS 48 standard-wall cycle estimate

A large standard-wall pipe has a moderate groove section, but every bead has a long circumference.

Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.

Inputs

Pipe & preparation
°
in
in
%
Passes & cycle
lb/in³
in²
in
in/min
in/min
in/min
min
min

Live weld sheet

Updated from inputs
Girth-weld groove sectionDeposited filler per joint 4.107 lb. Estimated passes 4. Joint arc time 90.53 min. Total joint cycle 120.53 min NET FILLER4.107lbPASS COUNT4ARC TIME90.53minJOINT CYCLE120.53min GIRTH-WELD GROOVE SECTION Wall 0.375 inR1 · H1 · F1 · C1NPS 48 CYCLE TIME BUDGETFAIL
Outside screen

Cycle time budget · 120.53 min planned vs 75 min budget.

Result details

Deposited filler per joint4.107 lb
Estimated passes4
Joint arc time90.53 min
Total joint cycle120.53 min
Effective wall0.375 in
Pipe outside diameter48 in
Pipe bore47.25 in
Groove centroid circumference149.93 in
Outside circumference150.8 in
Root circumference148.44 in
Groove mouth width0.42 in
Uncapped groove section0.086 in²
Groove and cap volume14.48 in³
Filler purchase per joint5.009 lb
Root passes1
Hot passes1
Fill passes1
Cap beads1
Cycle time margin-45.53 min

Worked example

Starting inputs

Nominal pipe size
NPS 48
Wall source
STD
Primary included angle
55 °
Root opening
0.094488 in
Root land
0.062992 in
Extra cap area
12 %
Overall filler process
FCAW

Baseline results

Deposited filler per joint
4.107 lb
Estimated passes
4
Joint arc time
90.53 min
Total joint cycle
120.53 min

The 0.086 in² groove runs around a 149.93 in centroid circumference before cap allowance. The sequence adds 1 root, 1 hot, 1 fill and 1 cap passes over 90.53 min of arc time.

Try it. Compare the cycle failure with the arc-only time. The difference is your allowance for work done between passes.

Calculation method

V = ∫ 2πr·w(r)dr + A꜀·π·OD · Arc time = Σ pass length / travel speed

The model integrates the piecewise linear groove width at each radius. Cap reinforcement is a percentage of groove area revolved at the outside diameter. Schedule presets cover a subset of common B36.10 walls. Confirm actual wall and ovality at the joint.

Reserve one root pass and an optional hot pass. Cap beads must cover the groove mouth and deposit the entered extra cap area. Root, hot and cap allowances are 0.60, 0.75 and 0.80 times the entered fill area per pass. Apply the unused cap-bead area to the groove, then round up the remaining fill passes. Root, hot/fill and cap times use the root, centroid and outside circumferences.

Cycle time adds the entered fit-up, interpass and handling allowance. Actual pass placement, reinforcement profile, deposition rates and essential variables come from the qualified procedure.

References

More worked examples