API 1104 · ASME B31.3
NPS 24 measured-wall line pipe
The incoming pipe lot is measured at 15.9 mm wall. Use measured thickness for the filler and time plan.
Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.
Inputs
Live weld sheet
Updated from inputsCycle time budget · 100.09 min planned vs 90 min budget.
Result details
| Deposited filler per joint | 2.488 kg |
|---|---|
| Estimated passes | 8 |
| Joint arc time | 72.09 min |
| Total joint cycle | 100.09 min |
| Effective wall | 15.9 mm |
| Pipe outside diameter | 609.6 mm |
| Pipe bore | 577.8 mm |
| Groove centroid circumference | 1,880.49 mm |
| Outside circumference | 1,915.11 mm |
| Root circumference | 1,815.21 mm |
| Groove mouth width | 18.681 mm |
| Uncapped groove section | 152.943 mm² |
| Groove and cap volume | 316.9 cm³ |
| Filler purchase per joint | 3.034 kg |
| Root passes | 1 |
| Hot passes | 1 |
| Fill passes | 4 |
| Cap beads | 2 |
| Cycle time margin | -10.09 min |
Worked example
Starting inputs
- Nominal pipe size
- NPS 24
- Wall source
- Measured wall
- Measured wall thickness
- 15.9 mm
- Primary included angle
- 60 °
- Root opening
- 2.4 mm
- Root land
- 1.8 mm
- Overall filler process
- FCAW
Baseline results
- Deposited filler per joint
- 2.488 kg
- Estimated passes
- 8
- Joint arc time
- 72.09 min
- Total joint cycle
- 100.09 min
The 152.943 mm² groove runs around a 1,880.49 mm centroid circumference before cap allowance. The sequence adds 1 root, 1 hot, 4 fill and 2 cap passes over 72.09 min of arc time.
Try it. A larger pipe has a longer seam per pass. Extra beads add a full revolution to the planned arc time.
Calculation method
V = ∫ 2πr·w(r)dr + A꜀·π·OD · Arc time = Σ pass length / travel speed
The model integrates the piecewise linear groove width at each radius. Cap reinforcement is a percentage of groove area revolved at the outside diameter. Schedule presets cover a subset of common B36.10 walls. Confirm actual wall and ovality at the joint.
Reserve one root pass and an optional hot pass. Cap beads must cover the groove mouth and deposit the entered extra cap area. Root, hot and cap allowances are 0.60, 0.75 and 0.80 times the entered fill area per pass. Apply the unused cap-bead area to the groove, then round up the remaining fill passes. Root, hot/fill and cap times use the root, centroid and outside circumferences.
Cycle time adds the entered fit-up, interpass and handling allowance. Actual pass placement, reinforcement profile, deposition rates and essential variables come from the qualified procedure.