WeldMetalLab

API 1104 · ASME B31.3

NPS 36 narrow compound groove with SAW

A large rotated girth weld is planned with a narrow outer bevel and a high deposition process.

Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.

Inputs

Pipe & preparation
°
°
mm
Measure outwards from the top of the root land.
mm
mm
%
Passes & cycle
kg/m³
mm²
mm
mm/min
mm/min
mm/min
min
min

Live weld sheet

Updated from inputs
Girth-weld groove sectionDeposited filler per joint 4.128 kg. Estimated passes 6. Joint arc time 49.16 min. Total joint cycle 81.16 min NET FILLER4.128kgPASS COUNT6ARC TIME49.16minJOINT CYCLE81.16min GIRTH-WELD GROOVE SECTION Wall 19.05 mmR1 · H1 · F3 · C1NPS 36 CYCLE TIME BUDGETPASS
Pass · within screen

Cycle time budget · 81.16 min planned vs 95 min budget.

Result details

Deposited filler per joint4.128 kg
Estimated passes6
Joint arc time49.16 min
Total joint cycle81.16 min
Effective wall19.05 mm
Pipe outside diameter914.4 mm
Pipe bore876.3 mm
Groove centroid circumference2,825.87 mm
Outside circumference2,872.67 mm
Root circumference2,752.98 mm
Groove mouth width13.024 mm
Uncapped groove section168.927 mm²
Groove and cap volume525.89 cm³
Filler purchase per joint4.213 kg
Root passes1
Hot passes1
Fill passes3
Cap beads1
Cycle time margin13.84 min

Worked example

Starting inputs

Nominal pipe size
NPS 36
Wall source
Schedule 40
Bevel profile
Compound V
Primary included angle
65 °
Outer included angle
16 °
Depth to bevel break
5.8 mm
Root opening
2.5 mm

Baseline results

Deposited filler per joint
4.128 kg
Estimated passes
6
Joint arc time
49.16 min
Total joint cycle
81.16 min

The 168.927 mm² groove runs around a 2,825.87 mm centroid circumference before cap allowance. The sequence adds 1 root, 1 hot, 3 fill and 1 cap passes over 49.16 min of arc time.

Try it. The estimate treats the root, fill and cap as separate revolutions. Confirm root-process speed against the actual sequence.

Calculation method

V = ∫ 2πr·w(r)dr + A꜀·π·OD · Arc time = Σ pass length / travel speed

The model integrates the piecewise linear groove width at each radius. Cap reinforcement is a percentage of groove area revolved at the outside diameter. Schedule presets cover a subset of common B36.10 walls. Confirm actual wall and ovality at the joint.

Reserve one root pass and an optional hot pass. Cap beads must cover the groove mouth and deposit the entered extra cap area. Root, hot and cap allowances are 0.60, 0.75 and 0.80 times the entered fill area per pass. Apply the unused cap-bead area to the groove, then round up the remaining fill passes. Root, hot/fill and cap times use the root, centroid and outside circumferences.

Cycle time adds the entered fit-up, interpass and handling allowance. Actual pass placement, reinforcement profile, deposition rates and essential variables come from the qualified procedure.

References

More worked examples