API 1104 · ASME B31.3
NPS 48 standard-wall cycle estimate
A large standard-wall pipe has a moderate groove section, but every bead has a long circumference.
Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.
Inputs
Live weld sheet
Updated from inputsCycle time budget · 120.53 min planned vs 75 min budget.
Result details
| Deposited filler per joint | 4.107 lb |
|---|---|
| Estimated passes | 4 |
| Joint arc time | 90.53 min |
| Total joint cycle | 120.53 min |
| Effective wall | 0.375 in |
| Pipe outside diameter | 48 in |
| Pipe bore | 47.25 in |
| Groove centroid circumference | 149.93 in |
| Outside circumference | 150.8 in |
| Root circumference | 148.44 in |
| Groove mouth width | 0.42 in |
| Uncapped groove section | 0.086 in² |
| Groove and cap volume | 14.48 in³ |
| Filler purchase per joint | 5.009 lb |
| Root passes | 1 |
| Hot passes | 1 |
| Fill passes | 1 |
| Cap beads | 1 |
| Cycle time margin | -45.53 min |
Worked example
Starting inputs
- Nominal pipe size
- NPS 48
- Wall source
- STD
- Primary included angle
- 55 °
- Root opening
- 0.094488 in
- Root land
- 0.062992 in
- Extra cap area
- 12 %
- Overall filler process
- FCAW
Baseline results
- Deposited filler per joint
- 4.107 lb
- Estimated passes
- 4
- Joint arc time
- 90.53 min
- Total joint cycle
- 120.53 min
The 0.086 in² groove runs around a 149.93 in centroid circumference before cap allowance. The sequence adds 1 root, 1 hot, 1 fill and 1 cap passes over 90.53 min of arc time.
Try it. Compare the cycle failure with the arc-only time. The difference is your allowance for work done between passes.
Calculation method
V = ∫ 2πr·w(r)dr + A꜀·π·OD · Arc time = Σ pass length / travel speed
The model integrates the piecewise linear groove width at each radius. Cap reinforcement is a percentage of groove area revolved at the outside diameter. Schedule presets cover a subset of common B36.10 walls. Confirm actual wall and ovality at the joint.
Reserve one root pass and an optional hot pass. Cap beads must cover the groove mouth and deposit the entered extra cap area. Root, hot and cap allowances are 0.60, 0.75 and 0.80 times the entered fill area per pass. Apply the unused cap-bead area to the groove, then round up the remaining fill passes. Root, hot/fill and cap times use the root, centroid and outside circumferences.
Cycle time adds the entered fit-up, interpass and handling allowance. Actual pass placement, reinforcement profile, deposition rates and essential variables come from the qualified procedure.