Worked example · Vibrating Screen

Basalt scalping deck

An upper scalping deck receives coarse basalt before downstream crushing. More than half of its feed is above the opening.

Live results

Screen deck and material split

Edit inputs
Screen deck and material split Four live readings and a schematic of the selected material-handling configuration. Full values follow the diagram. DECK AREA54.76ft²PASS EFF.97.92%UNDERSIZE229.13TPHOVERSIZE290.87TPH VIBRATING DECKMATERIAL SPLITOpening 2.5 inDry deckFeed520 TPHOversize290.87 TPHUndersize229.13 TPHTop deck Required / installed area54.76%Installed deck meets the estimated target area.

Installed deck meets the estimated target area.

All calculated values
Required live deck area
54.76ft²
Estimated passing efficiency
97.918%
Undersize product
229.129TPH
Oversize product
290.871TPH
True undersize in feed
234TPH
Undersize retained on deck
4.871TPH
Deck area at 90% recovery
59.468ft²
Aperture base capacity
3.642TPH/ft²
Corrected unit capacity
3.935TPH/ft²
Oversize correction
1.15
Half-size correction
0.81
Deck position correction
1
Wet screening correction
1
Density correction
1.16

Inputs

Unit system
Operating inputs
TPH
%
%
Percent of total feed smaller than half the selected aperture.
in
lb/ft³
ft²
%
Drive & model factors
TPH/ft²
0 uses the aperture curve. Enter the passing capacity per unit area at the stated reference conditions.

Worked solution

Starting case in US units

  1. Apply the 45% undersize fraction to the 520 TPH feed, giving 234 TPH of true undersize.
  2. The corrected unit capacity is 3.93 TPH/ft². The area required for 88% passing efficiency is 54.76 ft².
  3. With 100 ft² installed, predicted passing efficiency is 97.92%, splitting into 229.13 TPH passing and 290.87 TPH retained.

Try it. Compare the true coarse proportion with the modeled oversize product. Their difference is under-aperture material retained on the deck.

More worked examples

Open a different starting case

Equations and assumptions

Aperture rating and corrections

C = C₀ · Fo · Fh · Fd · Fw · Fρ

The default C₀ is 2.2 × aperture(in)^0.55 short tons/h/ft². Reference conditions are 25% oversize, 40% half-size, 100 lb/ft³, top deck, dry screening and 90% recovery. Fo = 1 + 0.5(oversize fraction − 0.25), Fh = 1 + (half-size fraction − 0.40), and Fd = 1/0.9/0.8 by deck position (top/second/third respectively). Wet spray uses Fw = 1 + 0.3/(1 + aperture(in)²). Fρ scales with bulk density. The curve and corrections are illustrative VSMA-style estimates. Use an OEM rating and validate motion, media open area, bed depth and blinding before selection.

Live area and passing efficiency

A₉₀ = Qfeed · fᵤ / C   |   E = 1 − 0.1^(Ainstalled/A₉₀)
Arequired = A₉₀ · ln(1 − Etarget) / ln(0.1)

fᵤ is the fraction smaller than the aperture. This first-pass recovery curve is anchored at 90% for A₉₀. Its estimated recovery depends on the installed live area. Use a sampled and weighed feed and product mass balance to establish plant efficiency.

Stream split

Qpassing = Qfeed · fᵤ · E   |   Qretained = Qfeed − Qpassing

This model assumes coarse particles remain above the aperture. The oversize product includes unrecovered fines. Feed, passing and retained rates use the same mass basis.