Worked example · Thermal packaging

PUR dry-ice deep-frozen shipper

A rigid polyurethane assembly holds a deep-frozen payload with a dry-ice charge.

Reserve hold
40.01h
Heat leak
28.35W
Coolant use
0.179kg/h
Nominal hold
61.55h
Edit inputs

Inputs

Edit any value to recalculate.

Interior & insulation

Select a starting value for k or enter the tested value for the complete assembly.

m
m
m
mm
W/(m·K)
Thermal conditions
°C
°C
%
Coolant charge

Replace gel-pack defaults with a supplier’s measured phase-change enthalpy.

kg

Dry ice releases CO₂. Use packaging designed to vent it and follow the applicable handling and shipping requirements.

Heat leak and hold-time reserve

Heat leak and hold-time reserveThe reserve is held back from the nominal cooling budget. The timeline assumes a constant ambient and cavity temperature.Ambient31 °CPayload target-45 °CHeat leak 28.3 WLatent-energy budget0 h61.55 h nominalAvailable holdEnergy held in reserve

The reserve is held back from the nominal cooling budget. The timeline assumes a constant ambient and cavity temperature.

Calculation breakdown

Mid-wall heat-transfer area
1.32m²
Wall R-value
3.54m²·K/W
Latent energy available
6,281kJ
Phase-change enthalpy
571kJ/kg
Coolant phase temperature
-78.5°C
Hold time set aside
21.54h
Ambient-to-payload difference
76K
Heat leak with cavity at coolant phase temp.
40.84W

Work through this case

  1. Wall R-value 3.54m²·K/W
  2. Coolant use 0.179kg/h
  3. Reserve hold 40.01h

A colder payload increases conduction even with good insulation. Confirm the effective panel conductivity includes joints and the vented construction.

More worked examples

Open a case with its assumptions loaded, then edit the inputs.

Open base calculator

Formulas and assumptions

Six-face heat leak

R = thickness / k • Q = A × (Tambient − Tpayload) / R

Area is measured at the wall mid-plane using interior dimensions plus one wall thickness. This case assumes the cavity follows the payload target. The readout also shows the higher heat leak if the whole cavity approaches the coolant phase temperature.

Coolant consumption

Rate = 3.6 × Q(W) / L(kJ/kg)

Dry ice uses 571 kJ/kg, about 246 BTU/lb, at −78.5 °C. The 0 °C and −21 °C phase-change pack enthalpies are adjustable starting values.

Reserve and qualification

treserve = m / rate × (1 − reserve fraction)

Budget for seams, bridges, air exchange, payload preconditioning, and ambient extremes. Verify the actual pack-out by an instrumented test against its approved qualification protocol and payload limits.

References

Questions and answers

What should I check in the pur dry-ice deep-frozen shipper example?

A colder payload increases conduction even with good insulation. Confirm the effective panel conductivity includes joints and the vented construction.