Offset CG puts one crane over the 75% cap

The CG of a 48 metric t module lies 3 m from crane A’s hook and 8 m from crane B’s hook.

Inputs

Payload and beam
metric t
m
m
metric t
%
Projected horizontal position, 0% at A and 100% at B.
Chart at worst lift position
metric t
metric t
metric t
metric t
Back to results ↑

Results

Static screeningEdit inputs ↓
Dual-hook free-body sketchCRANE A LOAD36.46metric tCRANE B LOAD14.79metric tA CAP MARGIN-3.46metric tB CAP MARGIN12.58metric tCRANE ACRANE BPAYLOAD CG / HOOK SPANA / 75% chart cap110.48%B / 75% chart cap54.03%Crane ACrane BPayload centerlineLift screening only · verify with rigger / PE and OEM chart

Schematic geometry. Margin bars mark 100% of the entered limit.

Review required
  • Crane A exceeds its 75% chart-capacity screening cap.
Gross demand on crane A
36.46 metric t
Gross demand on crane B
14.79 metric t
Crane A margin to 75% cap
-3.46 metric t
Crane B margin to 75% cap
12.58 metric t
Crane A chart capacity used
82.86 %
Crane B chart capacity used
40.52 %
Combined lifted weight
51.25 metric t

The shorter lever arm has the higher reaction. Review crane A’s margin separately even if the combined chart capacities look generous.

Gross demand on crane A 36.46 metric t · Gross demand on crane B 14.79 metric t

Payload reactions

Wₐ = W × b/(a + b), Wᵦ = W × a/(a + b)

Use projected horizontal distances from CG to the vertical lines. For unrotated lug coordinates, rotate them to the specified attitude before resolving reactions.

Gross hook demands

Gross share = payload share + beam share + hook gear

Use the beam CG location for its share. With gross chart capacities, include each hook block and applicable chart deductions once in gear.

Screening margin

Margin = 0.75 × chart capacity − gross share

The 75% cap is this tool’s planning assumption. Site procedures and the actual OEM load chart govern.

Use the weakest chart point at each actual radius, boom configuration and set-up. A qualified person must plan the lift under OSHA 1926.1432 where it applies. This is a static snapshot for vertical lines. Review dynamic load transfer and any off-plumb line separately.

Other worked examples