OSHA 1926.1432 · Multiple cranes

Tandem lift with an offset equalizer CG

The 9,000 lb equalizer CG is 72% of the way from hook A to hook B. The payload CG is nearer A.

Inputs

Payload and beam
lb
ft
ft
lb
%
Projected horizontal position, 0% at A and 100% at B.
Chart at worst lift position
lb
lb
lb
lb
Back to results ↑

Results

Static screeningEdit inputs ↓
Dual-hook free-body sketchCRANE A LOAD46,720lbCRANE B LOAD36,180lbA CAP MARGIN3,530lbB CAP MARGIN10,320lbCRANE ACRANE BPAYLOAD CG / HOOK SPANA / 75% chart cap92.98%B / 75% chart cap77.81%Crane ACrane BPayload centerlineLift screening only · verify with rigger / PE and OEM chart

Schematic geometry. Margin bars mark 100% of the entered limit.

Screening results

Compare these results with the approved equipment and lift plan.

Gross demand on crane A
46,720 lb
Gross demand on crane B
36,180 lb
Crane A margin to 75% cap
3,530 lb
Crane B margin to 75% cap
10,320 lb
Crane A chart capacity used
69.73 %
Crane B chart capacity used
58.35 %
Combined lifted weight
82,900 lb

Resolve the equalizer and payload as separate loads. Add the individual hook gear before applying the chart cap.

Gross demand on crane A 46,720 lb · Gross demand on crane B 36,180 lb

Payload reactions

Wₐ = W × b/(a + b), Wᵦ = W × a/(a + b)

Use projected horizontal distances from CG to the vertical lines. For unrotated lug coordinates, rotate them to the specified attitude before resolving reactions.

Gross hook demands

Gross share = payload share + beam share + hook gear

Use the beam CG location for its share. With gross chart capacities, include each hook block and applicable chart deductions once in gear.

Screening margin

Margin = 0.75 × chart capacity − gross share

The 75% cap is this tool’s planning assumption. Site procedures and the actual OEM load chart govern.

Use the weakest chart point at each actual radius, boom configuration and set-up. A qualified person must plan the lift under OSHA 1926.1432 where it applies. This is a static snapshot for vertical lines. Review dynamic load transfer and any off-plumb line separately.