Worked example · Line balance
Cabinet assembly three-station takt
Check throughput and minimum station count for cabinet assembly, inspection, and pack-out over a long shift.
Takt = Net available time ÷ Demand
Baseline reading
The three stations carry 333 seconds of work at a 120-second takt. Station 2 permits a modeled 244 units per shift.
What to test
Stress test the inspection cycle on heavy cabinet variants. Allow for safe handling and setup before committing the four-unit theoretical headroom.
Worksheet inputs
Inputs
Results
- Takt time
- 120 sec
- Bottleneck station
- Station 2
- Bottleneck cycle
- 118 sec
- Maximum steady-state shift output
- 244
- Output minus demand
- 4
- Net available shift time
- 28,800 sec
- Total work content
- 333 sec
- Theoretical station equivalents
- 2.775
- Minimum whole stations
- 3
- Line balance efficiency
- 94.0678%
- Balance delay
- 5.9322%
Model notes
Use station times for one unit, with the same product and work method. Maximum output assumes a staffed, paced line in steady state and excludes start-up fill and starvation.
The minimum whole-station count is a workload bound. Precedence, indivisible tasks, tooling and travel can require more operators or stations.
Frequently asked questions
Should two-person cabinet handling count as one station or two?
Enter the time between units for the station and track both assigned people for labor. Staffing inferred from work content assumes a consistent one-operator station unless adjusted separately.
Does 244 units include the first cabinet filling an empty line?
The calculation uses an established flow and full net time at the bottleneck rate. Add the fill and drain timing for a short run starting empty.