Worked example · Line balance
Gearbox assembly bottleneck
Use four gearbox assembly station cycles to diagnose a 400-unit shift demand gap.
Takt = Net available time ÷ Demand
Baseline reading
The torque station at 74 seconds exceeds the 66-second takt. On this model, the line can complete 356 units after fill.
What to test
Try moving a short verification step from station 3 to station 4. Confirm that torque recording remains in sequence and the receiving station stays below takt.
Worksheet inputs
Inputs
Results
- Takt time
- 66 sec
- Bottleneck station
- Station 3
- Bottleneck cycle
- 74 sec
- Maximum steady-state shift output
- 356
- Output minus demand
- -44
- Net available shift time
- 26,400 sec
- Total work content
- 233 sec
- Theoretical station equivalents
- 3.5303
- Minimum whole stations
- 4
- Line balance efficiency
- 78.7162%
- Balance delay
- 21.2838%
Model notes
Use station times for one unit, with the same product and work method. Maximum output assumes a staffed, paced line in steady state and excludes start-up fill and starvation.
The minimum whole-station count is a workload bound. Precedence, indivisible tasks, tooling and travel can require more operators or stations.
Frequently asked questions
How much of a 74-second torque station should move to hit gearbox takt?
A reduction to 66 seconds needs at least eight seconds of work removed, reassigned, or overlapped under the same quality controls.
Should torque-tool recalibration time go into each cycle?
For a scheduled shift-wide calibration break, deduct its duration from available time. For recurring per-unit tasks, include the observed cycle allowance at the station.