Worked example · Equipment effectiveness
Injection molding shift OEE
Audit a 450-minute injection molding shift with short feed interruptions, planned setup, and first-piece rejects.
OEE = Availability × Performance × Quality
Baseline reading
The press delivered 1,050 good parts. At 20 seconds each, they represent 350 ideal production minutes out of the 450 planned.
What to test
Log minor stops against the loader or resin feed. Compare that bucket with the loss from longer unplanned stops before choosing a repair.
Worksheet inputs
Inputs
Results
- Overall equipment effectiveness
- 77.7778%
- Total effective equipment performance
- 24.3056%
- Availability
- 91.1111%
- Performance
- 87.8049%
- Quality
- 97.2222%
- Calendar utilization
- 31.25%
- Run time
- 410 min
- First-pass good parts
- 1,050
- Ideal planned output
- 1,350 units
- Lost to downtime
- 120 units
- Lost to slow cycles and minor stops
- 150 units
- Lost to scrap or rework
- 30 units
- Unplanned stop loss
- 90 units
- Setup and adjustment loss
- 30 units
- Minor-stop loss
- 21 units
- Reduced-speed loss
- 129 units
- Production rejects
- 18
- Startup rejects
- 12
Model notes
Count each first-pass reject once. Use the ideal rate for the product being run and reconcile shift counts against the same production window.
The waterfall translates time losses into good-unit equivalents. Once stops and speed losses are removed, each rejected part reduces first-pass good output by one unit.
Frequently asked questions
How should blocked cavities affect this molding cycle?
Use an ideal seconds-per-part value derived from full qualified cavity output and include all parts at the counting point. Record an intentionally approved reduced-cavity standard as a separate operating condition.
Can runners and sprues be counted as molding rejects?
Use the qualified saleable part as the output unit. Report runner and sprue material as material yield or scrap cost under the plant accounting rule.