Equipment effectiveness
OEE, TEEP & Six Big Losses Calculator
Calculate overall equipment effectiveness, TEEP, availability, performance, quality, and lost good units from downtime, slow cycles, and rejects.
OEE = Availability × Performance × Quality
Worksheet inputs
Inputs
Results
- Overall equipment effectiveness
- 77.3333%
- Total effective equipment performance
- 24.1667%
- Availability
- 88.8889%
- Performance
- 90%
- Quality
- 96.6667%
- Calendar utilization
- 31.25%
- Run time
- 400 min
- First-pass good parts
- 696
- Ideal planned output
- 900 units
- Lost to downtime
- 100 units
- Lost to slow cycles and minor stops
- 80 units
- Lost to scrap or rework
- 24 units
- Unplanned stop loss
- 80 units
- Setup and adjustment loss
- 20 units
- Minor-stop loss
- 16 units
- Reduced-speed loss
- 64 units
- Production rejects
- 16
- Startup rejects
- 8
Model notes
Count each first-pass reject once. Use the ideal rate for the product being run and reconcile shift counts against the same production window.
The waterfall translates time losses into good-unit equivalents. Once stops and speed losses are removed, each rejected part reduces first-pass good output by one unit.
Frequently asked questions
Which denominator separates OEE from TEEP?
OEE uses scheduled production time. TEEP divides the ideal time represented by good parts by the full calendar time, including unscheduled nights and weekends.
Where should a five-minute changeover go in OEE?
If the machine was scheduled to produce, record the changeover as setup and adjustment downtime. Time outside the production schedule belongs in the calendar utilization gap.
What should I investigate when performance would exceed 100%?
Reconcile the ideal cycle time, counter multipliers, and the time window. Parallel cavities or an incorrect downtime total can make the measured output appear faster than the nominated ideal rate.