Worked example · Equipment effectiveness
Robotic welding cell OEE
Model a welding fixture outage, slowdown, and first-pass weld failures in a planned day shift.
OEE = Availability × Performance × Quality
Baseline reading
With a 54-second ideal cycle and 336 first-pass good assemblies, the fully productive equivalent is 302.4 minutes.
What to test
Check whether the outage came from fixture release or weld equipment. A downtime counter that can distinguish those events makes the next improvement more targeted.
Worksheet inputs
Inputs
Results
- Overall equipment effectiveness
- 67.2%
- Total effective equipment performance
- 21%
- Availability
- 83.3333%
- Performance
- 84%
- Quality
- 96%
- Calendar utilization
- 31.25%
- Run time
- 375 min
- First-pass good parts
- 336
- Ideal planned output
- 500 units
- Lost to downtime
- 83.33 units
- Lost to slow cycles and minor stops
- 66.67 units
- Lost to scrap or rework
- 14 units
- Unplanned stop loss
- 66.67 units
- Setup and adjustment loss
- 16.67 units
- Minor-stop loss
- 16.67 units
- Reduced-speed loss
- 50 units
- Production rejects
- 10
- Startup rejects
- 4
Model notes
Count each first-pass reject once. Use the ideal rate for the product being run and reconcile shift counts against the same production window.
The waterfall translates time losses into good-unit equivalents. Once stops and speed losses are removed, each rejected part reduces first-pass good output by one unit.
Frequently asked questions
When should a weld touch-up reduce OEE quality?
If the assembly needs touch-up to meet the weld acceptance criteria, count it once as a first-pass reject at that gate.
How do paired weld fixtures change the ideal cycle input?
Use the qualified effective seconds per discharged assembly if fixtures alternate within the same repeatable cell cycle.