FactoryOEELab

Worked example · Line balance

Label and pack line efficiency

Measure balance delay on a tightly paced six-station label and pack line with 600-unit shift demand.

Takt = Net available time ÷ Demand

Baseline reading

The line uses 247 of 258 available station-seconds per cycle at its 43-second pace. All six stations fit under the 44-second target.

What to test

Run the worksheet using realistic worst-case station averages from the busy mix. The nominal one-second bottleneck margin is sensitive to scan retries and replenishment.

Currency labels entered amounts. Exports record the selected display units.

Inputs

Shift and demand
sec
sec
Observed workstation cycles
sec
sec
sec
sec
sec
sec

Results

Takt time
44 sec
Bottleneck station
Station 3
Bottleneck cycle
43 sec

Every entered station is at or below customer takt.

Yamazumi station balance
Yamazumi station balance Station cycle bars with the dashed takt threshold. Ochre identifies stations above takt. CUSTOMER TAKT 44 sec012.324.63749.3Station 142Station 241Station 343Station 442Station 540Station 639sec
Maximum steady-state shift output
613
Output minus demand
13
Net available shift time
26,400 sec
Total work content
247 sec
Theoretical station equivalents
5.61364
Minimum whole stations
6
Line balance efficiency
95.7364%
Balance delay
4.2636%

Model notes

Use station times for one unit, with the same product and work method. Maximum output assumes a staffed, paced line in steady state and excludes start-up fill and starvation.

The minimum whole-station count is a workload bound. Precedence, indivisible tasks, tooling and travel can require more operators or stations.

View the equations

Frequently asked questions

Does high packing balance efficiency imply plenty of delivery margin?

The numbers answer different questions. This line is balanced at its current cycle and still has only one second between its slowest station and takt.

How should label roll replacement be time-studied?

Log its frequency and duration. Treat predictable line-wide stoppage as scheduled loss or model an effective per-unit time, using a consistent method across scenarios.