Worked example · Line balance
Medical kit packaging line balance
Balance five medical kit stations against demand for 420 completed kits per shift.
Takt = Net available time ÷ Demand
Baseline reading
The slowest station meets customer pace exactly at 60 seconds per kit. The calculated headroom is zero at that station.
What to test
Measure packaging verification with the intended material presentation and count replenishment intervals separately. A line at takt can miss target when either varies.
Worksheet inputs
Inputs
Results
- Takt time
- 60 sec
- Bottleneck station
- Station 3
- Bottleneck cycle
- 60 sec
- Maximum steady-state shift output
- 420
- Output minus demand
- 0
- Net available shift time
- 25,200 sec
- Total work content
- 269 sec
- Theoretical station equivalents
- 4.48333
- Minimum whole stations
- 5
- Line balance efficiency
- 89.6667%
- Balance delay
- 10.3333%
Model notes
Use station times for one unit, with the same product and work method. Maximum output assumes a staffed, paced line in steady state and excludes start-up fill and starvation.
The minimum whole-station count is a workload bound. Precedence, indivisible tasks, tooling and travel can require more operators or stations.
Frequently asked questions
Can final pouch sealing run at takt without any buffer?
The point estimate meets demand, while ordinary cycle variation and downtime can create a shortfall. Size any buffer using observed interruptions and lot-traceability rules.
Where should line clearance go in a medical kit shift model?
Deduct a planned clearance from available time when the line must stop. For clearances per batch, use the expected frequency for that shift.