NFPA 20 · Worked example

Pressure maintenance versus one open head

An existing aboveground loop is estimated to lose 14 GPM. The small sprinkler selected for comparison flows 12 GPM.

Inputs

Measured net pump points
GPM
psi
psi
psi
psi
psi

Evaluate suction at the governing pump flow.

Driver and pressure maintenance
%
%
hp

Use 0 when the full-curve maximum is unavailable.

%
GPM
GPM
psi

Three-point fire pump curve

Worksheet units
Edit inputs
Three-point fire pump curve · Input-linked engineering diagramCHURN HEAD127.1%150% HEAD75.3%DRIVER LOAD58hpSUCTION MARGIN20psiHead · % of ratedTest pointsNFPA limits01002000100150Flow · % of ratedSmaller pump-curve reserve+10.3 pp−25 pp0 pp limit+25 pp
Jockey flow reaches one head

For aboveground leakage service, review whether the jockey pump could mask an opened sprinkler.

How to read this example

The pressure-maintenance estimate reaches the single-sprinkler flow. Investigate leakage and verify that sprinkler operation will start the main pump.

Open the base calculator

Calculated values

Churn · percent of rated pressure
127.1 %
150% flow · percent of rated pressure
75.3 %
150% test flow
750 GPM
Reserve below 140% ceiling
12.9 pp
Reserve above 65% floor
10.3 pp
Flowing suction reserve
20 psi
Rated water power
24.8 hp
150% water power
28 hp
Rated shaft load
34.44 hp
150% shaft load
41.8 hp
Electric mechanical power estimate
58 hp
Diesel pre-derating power estimate
64.44 hp
Pressure maintenance flow estimate
14 GPM
Jockey discharge target
146 psi

Equations and assumptions

  • Churn ≤ 140% of rated net pressure
  • P_150 ≥ 65% of rated net pressure
  • Water hp = Q ΔP / 1714
  • BHP = water hp / pump efficiency

Enter net pump pressures at churn, rated flow and 150% flow. Use the listed full-curve peak BHP and the manufacturer’s site derating and driver data for selection.

The suction field screens a measured gauge pressure against the entered minimum. Confirm the adopted standard, the supply type, its available flow, intake arrangement and pump suction limits.

The jockey estimate uses at least 1 GPM or the entered leakage rate and aims for churn net pressure plus static suction. Compare with one sprinkler flow for aboveground-only pressure maintenance.