NFPA 13 · Worked example

Schedule 10 wet cross main

A 4 in. wet steel cross main carries 350 GPM for 280 ft. Fittings add 55 equivalent feet and the outlet is 8 ft higher.

Inputs

Pipe and roughness
Hydraulic path
GPM
psi
ft
ft
ft

A negative number represents a downhill run.

ft/s

Branch pressure section

Worksheet units
Edit inputs
Branch pressure section · Input-linked engineering diagramNET DROP12.9psiOUTLET85.1psiVELOCITY7.88ft/sPIPE BORE4.26inIN 98 psiOUT 85.1 psiC 120 · ID 4.26 inEq. 335 ftVelocity vs. project limit+7.12 ft/s0 ft/s15 ft/s target30 ft/s
Within velocity screen

Velocity is within the entered limit. Use outlet pressure in the next hydraulic segment.

How to read this example

Keep fitting loss separate from static head when carrying the outlet pressure into the next segment.

Open the base calculator

Calculated values

Net segment pressure drop
12.9 psi
Predicted outlet pressure
85.1 psi
Mean water velocity
7.88 ft/s
Velocity headroom
7.12 ft/s
Internal pipe diameter
4.26 in
Hazen–Williams C
120
Friction gradient
0.02818 psi/ft
Total equivalent length
335 ft
Straight-pipe loss
7.89 psi
Fitting loss
1.55 psi
Friction subtotal
9.44 psi
Signed elevation loss
3.46 psi

Equations and assumptions

  • p = 4.52 (Q/C)¹·⁸⁵ / d⁴·⁸⁷
  • ΔP = p (L + L_eq) + 0.433 Δz
  • v = Q / cross-sectional area

The U.S. equation uses GPM, actual internal diameter in inches and equivalent length in feet. The pressure gradient is in psi per foot.

Enter fitting lengths for the actual sizes, valves and C-factor. C = 100 is the conventional dry/preaction steel selection. Confirm permitted alternatives for the installed system.

Velocity is screened against an editable project criterion. The calculation uses one pipe segment at a steady flow.