GasCompressLab

API 618 · GPSA §13

Clearance pocket derating

A two-stage gatherer runs at 62% clearance on a high pressure-ratio selection.

What to check

Clearance re-expansion cuts delivered volume. The screen quantifies this penalty even when the process duty remains fixed.

Operating readout

Edit inputs ↓
Stage ratio
2.821×
Peak temp
149.7°C
Total power
63.14kW
Cylinder VE
29.09%
Cylinder temperature limit exceededA cylinder exceeds the selected service screening temperature.
Cylinder train and stage discharge temperaturesCYLINDERS & INTERCOOLERSkPa(a)CYL 1621CYL 21700DISCHARGE TEMPERATURE°C · r 2.8215032STG 1STG 2CYLINDER DELIVERY29.1% VE
Each cylinder uses the solved common ratio. Intercooler symbols mark where pressure is lost and temperature is reset.
Calculated details
Peak static gas rod load
20.37kN
Rod load utilization
16.29%
Total intercooler duty
29.55kW
Single-stage gas power
71.08kW
Power reduction vs single-stage
11.16%
Service temperature screen
135°C
Temperature margin
-14.7K
Hydrogen vendor shutdown example
—
Mass flow used
678.59kg/h

Stage schedule

  1. Stage 1

    Suction
    220kPa(a)
    Discharge
    620.62kPa(a)
    Outlet temp
    141.54°C
    Gas power
    31.27kW
    Cooler duty
    29.55kW
    Gas rod load
    7.38kN
  2. Stage 2

    Suction
    602.62kPa(a)
    Discharge
    1,700kPa(a)
    Outlet temp
    149.7°C
    Gas power
    31.88kW
    Cooler duty
    0kW
    Gas rod load
    20.37kN

Operating inputs

Stage duty
kPa(a)
kPa(a)
°C
°C
kPa
Nm³/h
Gas and cylinder
kg/kmol
%
%
mm
mm
kN

Calculation basis

Solve the pressure ladder

For each cylinder use P_out = rP_in. Subtract the entered pressure loss before the next stage. Solve r until the final discharge matches the target. Without losses r = (P_final/P₁)^(1/N).

Cylinder load and cooling

Clearance-only ηᵥ = 1 − c(r^(1/k) − 1). Use the full bore and rod-side annulus to estimate the maximum static differential gas load. Intercooler duty uses positive sensible heat removal only.

Related worked examples