CO₂ cylinder days for a 20×12 ft greenhouse

A 20×12×9 ft envelope has one modeled outdoor air change per hour. Use 420 ppm incoming air, a 950 ppm target and a 10-hour daily window.

Inputs

Growing space and concentration
ft
ft
ft
ppm
ppm
ACH

Zero is the ideal sealed-room calculation only.

Supply and operating schedule
CFH
lb

Enter the gas mass, such as 20 lb or 50 lb.

min
h/day

Results

Cylinder runtime at full flow

43.77 hours

Ideal-gas estimate near 20 °C and 1 atm

Room volume
2,160 ft³
Ideal no-exchange fill gas
32.417 L
Initial fill time at supply flow
7.29 min
Average flow to offset air exchange
1.145 CFH
Average holding duty
11.45 %
Equivalent on-time per cycle
1.72 min
Ideal fills per cylinder
382
Estimated cylinder life with daily refill
34.94 days

Ideal fill profile

The curve assumes well-mixed air and constant exchange.

Modeled CO₂ concentration rampIdeal well-mixed fill profile. The dashed line represents the planning target.CO₂ · ppm950420010 min

Worked calculation

  1. Convert the ppm increase to an ideal fill volume

    61,164.39 L × 530 ÷ 1,000,000 = 32.4171 L

  2. Calculate the air-exchange replacement flow

    32.4171 L × 1 ACH ÷ 60 = 0.5403 L/min

  3. Estimate the time to reach target from baseline

    −ln(1 − holding flow ÷ supply flow) ÷ (ACH ÷ 60) = 7.295 min

  4. Estimate cylinder gas volume and full-flow runtime

    50 lb = 22.6796 kg. Gas volume = 12,393.2 L. Divide by supply L/min and 60 = 43.77 h.

What the example shows

The computed steady replacement is 0.54 L/min. The calendar estimate includes both the initial ramp from incoming concentration and exchange replacement during the rest of the window.

How the model works

The room is modeled as well mixed, with constant incoming concentration and air exchange. Gas density is 1.83 g/L near 20 °C and 1 atm. Plant uptake, poor mixing, active ventilation changes and regulator behavior alter the result.

Equivalent timer on-time describes a cycle average. Peaks and troughs depend on cycle length, mixing, sensor placement and control response. Use a monitored controller supported by ventilation and independent safety alarms.

References

Common questions

How does opening the greenhouse vent affect the ten-hour cylinder estimate?

A change in ventilation changes the air-exchange rate and gas loss. Use operating conditions from the intended ventilation schedule when comparing scenarios.

Does the 20×12 model count CO₂ taken up by the crop?

It includes room volume, ventilation and the schedule. Crop uptake also affects gas use and can be seen in measured gas delivery and concentration under normal operation.