When a CO₂ supply cannot reach the greenhouse ppm target

The 512 ft³ room has 400 ppm incoming air and exchanges air twice per hour. A 0.5 CFH supply is being evaluated against a 1,000 ppm target.

Inputs

Growing space and concentration
ft
ft
ft
ppm
ppm
ACH

Zero is the ideal sealed-room calculation only.

Supply and operating schedule
CFH
lb

Enter the gas mass, such as 20 lb or 50 lb.

min
h/day

Results

Cylinder runtime at full flow

350.13 hours

Supply flow cannot reach the target at this air-exchange rate.

Room volume
512 ft³
Ideal no-exchange fill gas
8.699 L
Initial fill time at supply flow
—
Average flow to offset air exchange
0.614 CFH
Average holding duty
—
Equivalent on-time per cycle
—
Ideal fills per cylinder
569
Estimated cylinder life with daily refill
—

Ideal fill profile

The curve assumes well-mixed air and constant exchange.

Modeled CO₂ concentration rampIdeal well-mixed fill profile. The dashed line represents the planning target.CO₂ · ppm1000400030 min

Worked calculation

  1. Convert the ppm increase to an ideal fill volume

    14,498.23 L × 600 ÷ 1,000,000 = 8.6989 L

  2. Calculate the air-exchange replacement flow

    8.6989 L × 2 ACH ÷ 60 = 0.29 L/min

  3. Estimate the time to reach target from baseline

    Target requires a holding flow below the regulated supply flow.

  4. Estimate cylinder gas volume and full-flow runtime

    20 lb = 9.0718 kg. Gas volume = 4,957.3 L. Divide by supply L/min and 60 = 350.13 h.

What the example shows

The target requires about 0.29 L/min to offset exchange, while supply is about 0.24 L/min. The model marks the target unreachable. Maintain required ventilation and review the design with a qualified installer.

How the model works

The room is modeled as well mixed, with constant incoming concentration and air exchange. Gas density is 1.83 g/L near 20 °C and 1 atm. Plant uptake, poor mixing, active ventilation changes and regulator behavior alter the result.

Equivalent timer on-time describes a cycle average. Peaks and troughs depend on cycle length, mixing, sensor placement and control response. Use a monitored controller supported by ventilation and independent safety alarms.

References

Common questions

Why does this case show a tank runtime but no time to target?

The cylinder inventory and metered flow still define how long gas can be delivered. Exchange losses keep that flow from reaching the selected concentration.

Will extending the nominal timer interval fix a flow below the holding requirement?

No. Even continuous supply in this steady model is below the exchange loss at the target. Keep the ventilation design and get a qualified system review.