Industrial PLC distribution spares
A depot supports 80 PLCs with a 60-day lead time and 110,000-hour MTBF. Find a shelf stock target at 97% protection.
Stock covers the protection target
Inputs
- Fleet units M
- 80
- Unit MTBF
- 110,000 h
- Replenishment lead time
- 1,440 h
- Protection target P*
- 0.97 0–1
- Cost per spare
- 1,250 cost units
Results
- Minimum stock
- 3
- Protection
- 97.79753531 %
- Mean demand
- 1.047273
- Backorders
- 0.02734172
- Evaluated shelf stock
- 3 units
- Stockout probability
- 2.20246469 %
- Protection target
- 97 %
- Shelf inventory value
- 3,750 cost units
λ = M L / MTBFOver the replenishment window the fleet has mean demand 1.047273.Pr(D ≤ S) = Q(S+1, λ)For S = 3, the cycle protection probability is 0.97797535.S* = min {S ≥ 0 : Pr(D ≤ S) ≥ P*}The minimum whole stock is 3.EBO(S) = ∑ (d−S) Pr(D=d) for d > SExpected backlog is 0.02734172 units per lead-time window.
Demand is independent with constant rates and fixed replenishment lead time. Protection is cycle service probability Pr(D ≤ S). Inventory value is purchase cost times stocked units.