Hyperscale infrastructure case

Regional server PSU depot stock

A regional depot serves 3,200 PSUs with 250,000-hour MTBF and a 14-day lead time. Compare seven stocked spares with the 99.5% target.

Inputs

h
h
0–1
cost units
Blank uses the computed minimum stock.
FailStock falls below the protection target
Minimum stock
10
Protection
92.891%
Mean demand
4.3008
Backorders
0.122997

Lead-time demand and stock protection

Poisson demand probability and shelf-stock protectionDemand probability · PMF0%10.9%21.8%071320Lead-time demandStock protection · CDF0%50%100%071320Spare units on shelfProtectionStock / goal

Demand bars show the PMF and the line shows the cumulative probability of covering demand with a given stock level.

Download

Detailed results

Evaluated shelf stock
7 units
Stockout probability
7.10902619 %
Protection target
99.5 %
Shelf inventory value
1,820 cost units

Expected backorders measure units short per replenishment window. Stockout risk measures how often a shortage occurs.

Formula trace

  1. λ = M L / MTBFOver the replenishment window the fleet has mean demand 4.3008.
  2. Pr(D ≤ S) = Q(S+1, λ)For S = 7, the cycle protection probability is 0.92890974.
  3. S* = min {S ≥ 0 : Pr(D ≤ S) ≥ P*}The minimum whole stock is 10.
  4. EBO(S) = ∑ (d−S) Pr(D=d) for d > SExpected backlog is 0.1229965 units per lead-time window.

Model assumptions

Demand is independent with constant rates and fixed replenishment lead time. Protection is cycle service probability Pr(D ≤ S). Inventory value is purchase cost times stocked units.