API 1104 · ASME B31.3
NPS 6 Schedule 80 multipass girth weld
A heavy-walled NPS 6 process line uses a wider V and a discrete hot pass.
Engineering screening only. Verify the applicable code, material and qualified WPS/PQR before production use.
Inputs
Live weld sheet
Updated from inputsCycle time budget · 50.27 min planned vs 58 min budget.
Result details
| Deposited filler per joint | 0.393 kg |
|---|---|
| Estimated passes | 8 |
| Joint arc time | 34.27 min |
| Total joint cycle | 50.27 min |
| Effective wall | 10.97 mm |
| Pipe outside diameter | 168.275 mm |
| Pipe bore | 146.335 mm |
| Groove centroid circumference | 503.47 mm |
| Outside circumference | 528.65 mm |
| Root circumference | 459.72 mm |
| Groove mouth width | 15.066 mm |
| Uncapped groove section | 90.043 mm² |
| Groove and cap volume | 50.09 cm³ |
| Filler purchase per joint | 0.605 kg |
| Root passes | 1 |
| Hot passes | 1 |
| Fill passes | 4 |
| Cap beads | 2 |
| Cycle time margin | 7.73 min |
Worked example
Starting inputs
- Nominal pipe size
- NPS 6
- Wall source
- Schedule 80
- Primary included angle
- 65 °
- Root opening
- 3 mm
- Root land
- 1.5 mm
- Overall filler process
- SMAW
- Fill area per pass
- 15 mm²
Baseline results
- Deposited filler per joint
- 0.393 kg
- Estimated passes
- 8
- Joint arc time
- 34.27 min
- Total joint cycle
- 50.27 min
The 90.043 mm² groove runs around a 503.47 mm centroid circumference before cap allowance. The sequence adds 1 root, 1 hot, 4 fill and 2 cap passes over 34.27 min of arc time.
Try it. Narrower cap beads require more full revolutions. Compare the cap pass count and total cycle.
Calculation method
V = ∫ 2πr·w(r)dr + A꜀·π·OD · Arc time = Σ pass length / travel speed
The model integrates the piecewise linear groove width at each radius. Cap reinforcement is a percentage of groove area revolved at the outside diameter. Schedule presets cover a subset of common B36.10 walls. Confirm actual wall and ovality at the joint.
Reserve one root pass and an optional hot pass. Cap beads must cover the groove mouth and deposit the entered extra cap area. Root, hot and cap allowances are 0.60, 0.75 and 0.80 times the entered fill area per pass. Apply the unused cap-bead area to the groove, then round up the remaining fill passes. Root, hot/fill and cap times use the root, centroid and outside circumferences.
Cycle time adds the entered fit-up, interpass and handling allowance. Actual pass placement, reinforcement profile, deposition rates and essential variables come from the qualified procedure.