Worked example
Farm lane culvert below a 14 ac field
A farm access lane crosses drainage from 14 ac. The scenario combines compacted track and vegetated field cover, then screens a CMP barrel.
Estimate
Estimated peak runoff
- The barrel screen assumes steady full flow. A culvert design also checks inlet control, tailwater, headwater, debris and outlet conditions.
- Peak runoff · US gallons
- 6,635.1 US gpm
- Composite runoff coefficient
- 0.374
- Preliminary nominal pipe
- 30 in
- Theoretical full-flow diameter
- 28.37 in
- Selected barrel capacity
- 17.1578 ft³/s
- Full-flow velocity
- 3.495 ft/s
- Peak flow ÷ full area
- 3.012 ft/s
Download
Working this example
Starting estimate 14.783 ft³/sEstimated peak runoff
Review field contours, ditch paths and debris exposure. The surface area that drains to the crossing may change after grading.
Questions & answers
How do I choose acreage for this farm lane runoff estimate?
Delineate the land and connecting channels that drain to the crossing. Property lines matter only where they also define drainage divides.
Why does this farm-lane screen leave out debris blockage?
The barrel capacity assumes a clear, full circular section. Debris and entrance conditions require separate evaluation.