Worked example · Equipment effectiveness

Mixed-model appliance assembly OEE

Use an equivalent ideal cycle to study a mixed assembly shift with frequent planned model changes.

OEE = Availability × Performance × Quality

Baseline reading

Setup losses take 40 ideal parts of capacity, four times the unplanned stop loss. This example uses one representative standard across the mix.

What to test

For a live mixed-model report, sum each model’s ideal time by its actual counts. If rejects cluster by model, apply each model’s ideal time to good parts as well.

Currency labels entered amounts. Exports record the selected display units.

Inputs

Production window
min
min
min
min

Include all hours in the same period. Use 24 hours for one calendar day.

Production counts
min
Loss detail
min

Use the stop threshold in your plant reporting policy.

Results

Overall equipment effectiveness
76.4286%
Total effective equipment performance
22.2917%
Availability
88.0952%
Good-unit waterfall and APQ factors
Good-unit waterfall and APQ factors Waterfall from ideal production to first-pass good parts, followed by availability, performance, and quality factor bars. IDEAL GOOD-UNIT EQUIVALENTS420Ideal50Stops40Speed9Rejects321GoodAvailability88.1%Performance89.2%Quality97.3%
Performance
89.1892%
Quality
97.2727%
Calendar utilization
29.1667%
Run time
370 min
First-pass good parts
321
Ideal planned output
420 units
Lost to downtime
50 units
Lost to slow cycles and minor stops
40 units
Lost to scrap or rework
9 units
Unplanned stop loss
10 units
Setup and adjustment loss
40 units
Minor-stop loss
15 units
Reduced-speed loss
25 units
Production rejects
6
Startup rejects
3

Model notes

Count each first-pass reject once. Use the ideal rate for the product being run and reconcile shift counts against the same production window.

The waterfall translates time losses into good-unit equivalents. Once stops and speed losses are removed, each rejected part reduces first-pass good output by one unit.

View the equations

Frequently asked questions

Why might one average assembly cycle misstate mixed-model results?

A change in the proportion of long-cycle models can change ideal productive time even with identical equipment and operator performance.

Can tester hold time be recorded as an assembly stoppage?

Capture holds as availability loss if the scheduled line is stopped. If upstream production continues, use the measured constraint boundary and avoid counting the same loss twice.