Worked example · Equipment effectiveness
Carton packing line OEE
Evaluate a high-volume carton line where microstops and rejected seals compete with planned packaging adjustments.
OEE = Availability × Performance × Quality
Baseline reading
The line shipped 12,450 first-pass cartons on this count. The 1,200 seconds of remaining reduced-speed loss are separate from the 1,200 seconds logged as minor stops.
What to test
Review film-change and photoeye clearing events below the stop threshold, then compare their good-unit impact with seal rejects.
Worksheet inputs
Inputs
Results
- Overall equipment effectiveness
- 86.4583%
- Total effective equipment performance
- 43.2292%
- Availability
- 93.0556%
- Performance
- 94.0299%
- Quality
- 98.8095%
- Calendar utilization
- 50%
- Run time
- 670 min
- First-pass good parts
- 12,450
- Ideal planned output
- 14,400 units
- Lost to downtime
- 1,000 units
- Lost to slow cycles and minor stops
- 800 units
- Lost to scrap or rework
- 150 units
- Unplanned stop loss
- 600 units
- Setup and adjustment loss
- 400 units
- Minor-stop loss
- 400 units
- Reduced-speed loss
- 400 units
- Production rejects
- 130
- Startup rejects
- 20
Model notes
Count each first-pass reject once. Use the ideal rate for the product being run and reconcile shift counts against the same production window.
The waterfall translates time losses into good-unit equivalents. Once stops and speed losses are removed, each rejected part reduces first-pass good output by one unit.
Frequently asked questions
Do carton sensor retries count as new cartons?
Use unique physical cartons at the output counter. Exclude duplicate sensor transitions and retries from total production.
How can I isolate seal quality after a new film roll?
Time-stamp reject counts around roll changes. Assign startup rejects only within the window your team uses for qualified restart conditions.