Worked example · Shop costing
CNC turning quote with shared labor
Cost a short turning job while one operator tends two machines across the planned billable window.
Hourly rate = Annual burden ÷ Billable hours + Allocated labor
Baseline reading
The machine portion is 20 per hour and allocated labor is 24. The resulting 66 setup charge is spread over ten saleable parts.
What to test
Compare staffed setup with unattended running before finalizing the labor ratio. Reconcile whether a separate setup labor rate is required by your costing method.
Worksheet inputs
Inputs
Results
- All-in machine hourly rate
- $44.00/hr
- Total unit cost
- $14.51
- Quoted price per unit
- $18.14
| 10 units | $14.51 |
|---|---|
| 50 units | $9.23 |
| 250 units | $8.18 |
| 1,000 units | $7.98 |
- Total batch quote
- $181.41
- Setup amortized per unit
- $6.60
- Run cost per saleable unit
- $1.85
- Material per saleable unit
- $6.06
- Setup cost per batch
- $66.00
- Billable hours per year
- 3,000 hr
- Equipment burden rate
- $20.00/hr
- Allocated operator rate
- $24.00/hr
Model notes
The model uses straight-line depreciation with zero residual value and allocates annual machine costs over billable hours. Operator cost is spread over the stated machines per operator.
Run labor, machine time, and material are divided by yield. Setup is spread over the requested saleable quantity. Markup is applied to cost before taxes, freight, and selling adjustments.
Frequently asked questions
Can the turning batch use two-machine staffing during setup?
Use the ratio that reflects expected attendance. If setup requires exclusive attention, price that interval separately under the plant’s accepted method.
How can bar-remnant cost be captured in a turned part quote?
Include a material allowance per started part if remnants are a routine process loss. Keep the scrap input for starts that fail to become saleable parts.