Worked example · Shop costing
Vertical mill setup amortization
Build a vertical machining center rate and compare the per-part burden of a two-hour setup across batches.
Hourly rate = Annual burden ÷ Billable hours + Allocated labor
Baseline reading
The hourly rate is 30. Setup adds 1.20 per piece at 50 pieces, the run adds 0.75, and material adds 4.00.
What to test
Test the next batch tier against storage and order risk. Consider where a proven setup reduction has the largest unit-cost effect.
Worksheet inputs
Inputs
Results
- All-in machine hourly rate
- $30.00/hr
- Total unit cost
- $5.95
- Quoted price per unit
- $7.14
| 10 units | $10.75 |
|---|---|
| 50 units | $5.95 |
| 250 units | $4.99 |
| 1,000 units | $4.81 |
- Total batch quote
- $357.00
- Setup amortized per unit
- $1.20
- Run cost per saleable unit
- $0.75
- Material per saleable unit
- $4.00
- Setup cost per batch
- $60.00
- Billable hours per year
- 2,400 hr
- Equipment burden rate
- $10.00/hr
- Allocated operator rate
- $20.00/hr
Model notes
The model uses straight-line depreciation with zero residual value and allocates annual machine costs over billable hours. Operator cost is spread over the stated machines per operator.
Run labor, machine time, and material are divided by yield. Setup is spread over the requested saleable quantity. Markup is applied to cost before taxes, freight, and selling adjustments.
Frequently asked questions
Where should a probing and prove-out routine go on this mill?
Use setup time for one-off program prove-out and initial probing. Add repeat probing to the regular cycle.
Would a single-piece vertical mill quote recover a full setup?
The setup cost is divided over the saleable batch. With one piece, the full setup amount falls on that piece.