Machine Hourly Rate, Setup Amortization & Batch Quote Calculator
Build a CNC or machine-shop hourly rate from depreciation, burden, labor and utilization. Quote a batch and compare unit cost at four quantities.
Hourly rate = Annual burden ÷ Billable hours + Allocated labor
Worksheet inputs
Inputs
Results
- All-in machine hourly rate
- $43.94/hr
- Total unit cost
- $5.93
- Quoted price per unit
- $7.11
| 10 units | $12.26 |
|---|---|
| 50 units | $6.98 |
| 250 units | $5.93 |
| 1,000 units | $5.73 |
- Total batch quote
- $1,778.67
- Setup amortized per unit
- $0.26
- Run cost per saleable unit
- $0.97
- Material per saleable unit
- $4.69
- Setup cost per batch
- $65.91
- Billable hours per year
- 2,800 hr
- Equipment burden rate
- $15.94/hr
- Allocated operator rate
- $28.00/hr
Model notes
The model uses straight-line depreciation with zero residual value and allocates annual machine costs over billable hours. Operator cost is spread over the stated machines per operator.
Run labor, machine time, and material are divided by yield. Setup is spread over the requested saleable quantity. Markup is applied to cost before taxes, freight, and selling adjustments.
Frequently asked questions
Where should shared labor go when one operator tends several CNCs?
Divide the hourly burdened operator rate by the effective machines per operator for the job. Use a concurrency ratio that reflects attendance for setup, inspection, and handling.
Why does the quote rise when annual available hours stay flat?
Reduced billable utilization spreads depreciation and annual burden over fewer hours. The calculated allocated labor rate stays tied to the staffing ratio.
Does the quote markup field create the same percentage as gross margin?
For unit cost of 100 and markup of 20%, price is 120 and margin is 20 ÷ 120, or 16.67%. Enter markup on cost in this worksheet.