Worked example · Equipment effectiveness
Stamping press die-change OEE
Compare a stamping press’s one-hour die change with speed and reject losses over an eight-hour planned run.
OEE = Availability × Performance × Quality
Baseline reading
The die change consumed 300 ideal pieces of capacity. Of the 45 first-pass rejects, 25 came from startup.
What to test
Try a 45-minute die-change value and hold the remaining duration and count assumptions explicit. Check whether first-piece approval can move earlier without adding risk.
Worksheet inputs
Inputs
Results
- Overall equipment effectiveness
- 73.125%
- Total effective equipment performance
- 24.375%
- Availability
- 87.5%
- Performance
- 85.7143%
- Quality
- 97.5%
- Calendar utilization
- 33.3333%
- Run time
- 420 min
- First-pass good parts
- 1,755
- Ideal planned output
- 2,400 units
- Lost to downtime
- 300 units
- Lost to slow cycles and minor stops
- 300 units
- Lost to scrap or rework
- 45 units
- Unplanned stop loss
- 0 units
- Setup and adjustment loss
- 300 units
- Minor-stop loss
- 75 units
- Reduced-speed loss
- 225 units
- Production rejects
- 20
- Startup rejects
- 25
Model notes
Count each first-pass reject once. Use the ideal rate for the product being run and reconcile shift counts against the same production window.
The waterfall translates time losses into good-unit equivalents. Once stops and speed losses are removed, each rejected part reduces first-pass good output by one unit.
Frequently asked questions
When does a die-change clock stop for this study?
Use an agreed end point such as the first approved piece at standard conditions so comparisons include adjustment time consistently.
Where do small misfeed clears belong after die release?
Record short clears below your stop threshold as minor stops within production run time. Keep extended repairs with availability losses.