FactoryOEELab

Worked example · Equipment effectiveness

Stamping press die-change OEE

Compare a stamping press’s one-hour die change with speed and reject losses over an eight-hour planned run.

OEE = Availability × Performance × Quality

Baseline reading

The die change consumed 300 ideal pieces of capacity. Of the 45 first-pass rejects, 25 came from startup.

What to test

Try a 45-minute die-change value and hold the remaining duration and count assumptions explicit. Check whether first-piece approval can move earlier without adding risk.

Currency labels entered amounts. Exports record the selected display units.

Inputs

Production window
min
min
min
min

Include all hours in the same period. Use 24 hours for one calendar day.

Production counts
min
Loss detail
min

Use the stop threshold in your plant reporting policy.

Results

Overall equipment effectiveness
73.125%
Total effective equipment performance
24.375%
Availability
87.5%
Good-unit waterfall and APQ factors
Good-unit waterfall and APQ factors Waterfall from ideal production to first-pass good parts, followed by availability, performance, and quality factor bars. IDEAL GOOD-UNIT EQUIVALENTS2.4KIdeal300Stops300Speed45Rejects1.8KGoodAvailability87.5%Performance85.7%Quality97.5%
Performance
85.7143%
Quality
97.5%
Calendar utilization
33.3333%
Run time
420 min
First-pass good parts
1,755
Ideal planned output
2,400 units
Lost to downtime
300 units
Lost to slow cycles and minor stops
300 units
Lost to scrap or rework
45 units
Unplanned stop loss
0 units
Setup and adjustment loss
300 units
Minor-stop loss
75 units
Reduced-speed loss
225 units
Production rejects
20
Startup rejects
25

Model notes

Count each first-pass reject once. Use the ideal rate for the product being run and reconcile shift counts against the same production window.

The waterfall translates time losses into good-unit equivalents. Once stops and speed losses are removed, each rejected part reduces first-pass good output by one unit.

View the equations

Frequently asked questions

When does a die-change clock stop for this study?

Use an agreed end point such as the first approved piece at standard conditions so comparisons include adjustment time consistently.

Where do small misfeed clears belong after die release?

Record short clears below your stop threshold as minor stops within production run time. Keep extended repairs with availability losses.