Worked example · Shop costing

Vertical mill setup amortization

Build a vertical machining center rate and compare the per-part burden of a two-hour setup across batches.

Hourly rate = Annual burden ÷ Billable hours + Allocated labor

Baseline reading

The hourly rate is 30. Setup adds 1.20 per piece at 50 pieces, the run adds 0.75, and material adds 4.00.

What to test

Test the next batch tier against storage and order risk. Consider where a proven setup reduction has the largest unit-cost effect.

Currency labels entered amounts. Exports record the selected display units.

Inputs

Machine and billable capacity
$
yr
hr/yr
%
Annual burden and direct labor
$/yr
$/yr
$/yr
$/yr
$/hr
Batch quote
min
min
$
%
%

Results

All-in machine hourly rate
$30.00/hr
Total unit cost
$5.95
Quoted price per unit
$7.14
Batch quantity versus unit cost
Batch quantity versus unit cost Unit cost declines as the fixed setup is spread across more saleable units. The current batch is marked in ochre. UNIT COST / QUANTITY ON LOG SCALE$3.9$6.5$9.1$11.610502501KCurrent 50 pcs • $6/pc
Unit cost by batch
10 units$10.75
50 units$5.95
250 units$4.99
1,000 units$4.81
Total batch quote
$357.00
Setup amortized per unit
$1.20
Run cost per saleable unit
$0.75
Material per saleable unit
$4.00
Setup cost per batch
$60.00
Billable hours per year
2,400 hr
Equipment burden rate
$10.00/hr
Allocated operator rate
$20.00/hr

Model notes

The model uses straight-line depreciation with zero residual value and allocates annual machine costs over billable hours. Operator cost is spread over the stated machines per operator.

Run labor, machine time, and material are divided by yield. Setup is spread over the requested saleable quantity. Markup is applied to cost before taxes, freight, and selling adjustments.

View the equations

Frequently asked questions

Where should a probing and prove-out routine go on this mill?

Use setup time for one-off program prove-out and initial probing. Add repeat probing to the regular cycle.

Would a single-piece vertical mill quote recover a full setup?

The setup cost is divided over the saleable batch. With one piece, the full setup amount falls on that piece.